Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $1,407,000 for a total estimated cost of these projects being $1,674,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number

190038

Version

 SUBSTITUTE 1

Reference

181687

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $1,407,000 for a total estimated cost of these projects being $1,674,000.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $1,407,000.  The total estimated cost of these projects is $1,674,000.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

4th Aldermanic District

 

N. Broadway - E. Highland Ave. to E. Juneau Ave. (SM495180043) File Number 181687: Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $75,000, additional funds).   The total estimated cost of this project including the requested amount is $222,000).  This project is anticipated to be completed during the 2019 construction season. 

 

6th Aldermanic District

 

W. Capitol Dr. - N.  Richards St. to N. 2nd St. (WT410190780) File Number 190037:  Water main joint repair.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $185,000). The total estimated cost of this project including the requested amount is $200,000.  This project is anticipated to be completed during the 2019 construction season. 

 

W. Nash St. - 160’ east of N. 17th St. to N. 18th St. (SM494180031) File Number 180872:  Relaying storm sewer. Installing new storm sewer.  (Infiltration/Inflow Reduction Fund -- $149,000). The total estimated cost of this project including the requested amount is $161,000.  This project is anticipated to be completed during the 2019 construction season. 

 

7th Aldermanic District

 

N. 37th St. - W. Keefe Ave. to W. Nash St. (SM495180089) File Number 181118:

Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $164,000).

The total estimated cost of this project including the requested amount is $176,000.  This project is anticipated to be completed during the 2019 construction season. 

 

N. 44th St. - W. Concordia Ave. to W. Townsend St. (SM494180029) File Number 180872: Relaying Sanitary Sewer.  (Infiltration/Inflow Reduction Fund -- $90,000).  The total estimated cost of this project including the requested amount is $102,000.  This project is anticipated to be completed during the 2019 construction season. 

9th Aldermanic District

 

N. Edgeworth Dr. - 35’ northwest of W. Port Ave. to 140’ north west of N. 57th St. (SM494180050) File Number 181383: (Infiltration/Inflow Reduction Fund -- $103,000).  The total estimated cost of this project including the requested amount is $115,000.  This project is anticipated to be completed during the 2019 construction season. 

 

13th Aldermanic District

 

W. Barnard Ave. - S. 20th St. to S. 21st St.  (WT410190644)  File Number 171854: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $83,000).   The total estimated cost of this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2019 construction season. 

 

S. 21st St. - 300’ north of W. Barnard Ave. to W. Barnard Ave. (WT410190643) File Number 171854: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $88,000).   The total estimated cost of this project including the requested amount is $105,000.  This project is anticipated to be completed during the 2019 construction season. 

 

15th Aldermanic District

 

W. Clarke St. - N. 38th St. to N. 39th St. (SM495180068)  File Number 180872: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $65,000).   The total estimated cost of this project including the requested amount is $77,000.  This project is anticipated to be completed during the 2019 construction season. 

 

N. 38th St. - W. Wright St. to W. Center St. (SM495180069)  File Number 180872: Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $401,000).   The total estimated cost of this project including the requested amount is $416,000.  This project is anticipated to be completed during the 2019 construction season. 

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 