powered help
header-left header-center header-right
File #: 181686    Version:
Type: Resolution Status: Passed
File created: 2/26/2019 In control: COMMON COUNCIL
On agenda: Final action: 3/26/2019
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $199,000 for a total estimated cost of these projects being $3,364,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
181686
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $199,000 for a total estimated cost of these projects being $3,364,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $199,000 with the total cost estimated to be $3,364,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

2nd and 7th Aldermanic Districts

N. 60th St. - W. Capitol Dr. to W. Hampton Ave. (WT410200003) Hydrant alteration.
(Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $13,000). The total estimated cost of this project including the requested amount is $80,000. This project is anticipated to be completed during the 2020 construction season.

3rd Aldermanic District

N. Humboldt Ave. - E. North Ave. to E. Keefe Ave. (WT410200002) Hydrant alteration. (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $13,000). The total estimated cost of this project including the requested amount is $120,000. This project is anticipated to be completed during the 2020 construction season.

4th Aldermanic District

W. St. Paul Ave. -- N. 6th St. to N. Vel R. Phillips Ave. (SM495190013) Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $12,000.) The total estimated cost of this project including the requested amount is $115,000. This project is anticipated to be com...

Click here for full text