File #: 181577    Version: 0
Type: Resolution Status: Passed
File created: 2/5/2019 In control: COMMON COUNCIL
On agenda: Final action: 2/26/2019
Effective date:    
Title: Resolution directing the Commissioner of Public Works to execute project agreements titled State/Municipal Agreement for a State Let Urbanized Area STP-Urban Project with the Wisconsin Department of Transportation and to set up funds for design engineering at total estimated cost of $2,650,060 and an estimated City of Milwaukee share of $530,013 and a grantor share of $2,120,047.
Sponsors: THE CHAIR
Indexes: AGREEMENTS, PUBLIC IMPROVEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Grant Resolution Certification A, 2. Grant Resolution Certification B, 3. Grant Resolution Certification C, 4. Hampton Street SMA, 5. Walnut Street SMA, 6. Howard Avenue SMA

Number

181577

Version

Original

Reference

Sponsor

The Chair

Title

Resolution directing the Commissioner of Public Works to execute project agreements titled State/Municipal Agreement for a State Let Urbanized Area STP-Urban Project with the Wisconsin Department of Transportation and to set up funds for design engineering at total estimated cost of $2,650,060 and an estimated City of Milwaukee share of $530,013 and a grantor share of $2,120,047.

Analysis

This resolution authorizes and directs the Commissioner of Public Works to execute project agreements with the Wisconsin Department of Transportation for the programming, design and construction of local arterial Streets with 80 percent Federal and State aid under the Surface Transportation Program.  This resolution also directs the City of Milwaukee Comptroller to transfer funds and establish project grant chartfield values for the preliminary engineering for these projects.  The estimated total cost of the projects is $10,678,028 of which the City’s share is $2,427,533 and the grantor share is $8,250,495.  The estimated preliminary engineering cost for these projects is $2,650,060 which the City’s share is $530,013 and the grantor’s share is $2,120,047.  Construction funds for these projects will be included in future resolutions.

Body

Whereas, The project agreements have been requested and received from the Wisconsin Department of Transportation to be executed by the City of Milwaukee for the programming, design and construction of the following paving projects with Federal and State aid under the Surface Transportation Program:

 

State I.D. 2395-05-01, 71

East/West Howard Avenue - South 6th Street to South Clement Avenue

State I.D. 2674-02-00

West Walnut Street - North 20th Street to North 12th Street

State I.D. 2545-09-01

West Hampton Avenue - North 60th Street to North Teutonia Avenue

 

Whereas, The Department of Public Works shall notify the Common Council of the City of Milwaukee of project cost overruns and changes in scope approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be 100 percent liable for project cost overruns and changes in scope as approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be liable for any costs incurred by the State should the City decide to withdraw from the project; and

Whereas, Construction on these projects is currently scheduled to start in 2022-2023; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works is hereby directed to execute agreements for the programming, design and construction of the aforementioned projects with Federal and State aid under the Surface Transportation Program, copies of which are attached and are incorporated in this resolution by reference as though set forth in full; and, be it

 

Further Resolved, That the Commissioner of Public Works is hereby directed to undertake, or engage a consultant to undertake, design engineering for the improvement of the aforementioned projects and to reimburse the Wisconsin Department of Transportation for design engineering costs they incur for the improvement; and, be it

 

Further Resolved, that the Commissioner of Public Works is hereby authorized and directed to sign documents that are required if right-of-way acquisition is necessary as part of the project work; and, be it

 

Further Resolved, That the Commissioner of Public Works is hereby authorized and directed to enter into an agreement with the Wisconsin Department of Transportation pertaining to the cost participation for the installation and modification of traffic control facilities in conjunction with the improvements of the aforementioned projects; and, be it

 

Further Resolved, That the Commissioner of Public Works is hereby authorized and directed to negotiate and enter into cost sharing agreements with adjacent municipalities for those projects whose project limits extend beyond the City of Milwaukee boundaries; and, be it

 

Further Resolved, That the City Comptroller is hereby authorized to create within the Capital Improvement Fund, Grant and Aid Projects, the necessary Project Grant Chartfield Values for design engineering for the projects (Expenditure) and transfer to any of these accounts the amount required under the grant agreement and City Accounting Policy but not to exceed a 10 percent increase of the total amounts reserved for the grantor’s share and local share or $5,000, whichever is greater, as follows:

 

State I.D. 2395-05-01

East/West Howard Avenue - South 6th Street to South Clement Avenue

City Share Non-Assessable Fund Paving

ST320190000

Fund 0333

$218,945

Grantor Reimbursable Fund Paving

SP032190100

Fund 0306

$863,779

Grantor Non-Reimbursable Cash Fund Paving

$12,000

Estimated total engineering $1,094,724

Total engineering previously authorized -0-

Current estimated cost of total project including this resolution $9,122,692

Original estimated cost of total project $9,122,692

 

State I.D. 2674-02-00

West Walnut Street - North 20th Street to North 12th Street

City Share Non-Assessable Fund Paving

ST320190000

Fund 0333

$103,510

Grantor Reimbursable Fund Paving

SP032190100

Fund 0306

$402,038

Grantor Non-Reimbursable Cash Fund Paving

$12,000

Estimated total engineering $517,548

Total engineering previously authorized -0-

Current estimated cost of engineering including this resolution $517,548

Original estimated cost of total project $517,548

 

State I.D. 2545-09-01

West Hampton Avenue - North 60th Street to North Teutonia Avenue

City Share Non-Assessable Fund Paving

ST320190000

Fund 0333

$207,558

Grantor Reimbursable Fund Paving

SP032190100

Fund 0306

$818,230

Grantor Non-Reimbursable Cash Fund Paving

$12,000

Estimated total engineering $1,037,788

Total engineering previously authorized -0-

Current estimated cost of engineering including this resolution $1,037,788

Original estimated cost of total project $1,037,788

 

Totals

 

City Share Non-Assessable Fund Paving $530,013

Grantor Reimbursable Fund Paving $2,084,047

Grantor Non-Reimbursable Cash Fund Paving $36,000

Estimated Total $2,650,060; and, be it

 

Further Resolved, That the City Engineer is hereby authorized and directed to approve and make periodic payments to the Wisconsin Department of Transportation upon receipt of invoices for the City’s share of costs of the above projects.

 

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

Chad T. Chrisbaum: Cheryl Murphy

January 25, 2019

Technical Correction

MKS

2/11/19