powered help
header-left header-center header-right
File #: T84    Version: 0
Type: Travaux Resolution Status: Passed
File created: 11/9/2018 In control: TRAVAUX INC. BOARD OF DIRECTORS
On agenda: 11/14/2018 Final action: 11/14/2018
Effective date:    
Title: Resolution approving a contract to Thomas A. Mason Company Incorporated (Milwaukee, WI) for Paintings and Wall Coverings for the Multi-Family Apartment Building 2.3 at Westlawn Gardens Phase 2 in the amount of $163,597.00 (Official Notice No. 57909)
Sponsors: THE CHAIR
Attachments: 1. 57909 IFB tab WLG Ph2 Multi-Fam Apt Bldg 2.3 Painting & Wall Covering Thomas A Mason, 2. 57909 EBE-Sec3 Review Thomas A Mason WLG Ph2 Bldg 2.3 Painting & Wall Coverings 11-09-18

Number

T84

 

Version

Original

 

Reference

 

Sponsor

The President

 

Title

Resolution approving a contract to Thomas A. Mason Company Incorporated (Milwaukee, WI) for Paintings and Wall Coverings for the Multi-Family Apartment Building 2.3 at Westlawn Gardens Phase 2 in the amount of $163,597.00 (Official Notice No. 57909)

 

Analysis

 

Body

WHEREAS, Travaux Inc. solicited sealed bids by Official Notice Number 57909 during the period October 12, 2018 through November 2, 2018 for Painting and Wall Coverings for Multi-Family Apartment Building 2.3 at Westlawn Gardens Phase 2; and

 

WHEREAS, three sealed bids were received by the deadline of 2:00 PM (CDST) on November 2, 2018; and

 

WHEREAS, the sealed bids were received and publicly opened on November 2, 2018, during which bidding procedure was conducted in compliance with the requirements of local, state, and federal regulations; and

 

WHEREAS, Thomas A. Mason Co. Inc., the lowest bidder and a qualified and competent bidder, submitted the lowest responsive and responsible bid in the amount of $163,597.00 therefore, be it

 

RESOLVED, by the Board of Directors of Travaux Inc. that they hereby authorize and approve accepting the bid of and entering into a contract with Thomas A. Mason Co. Inc. for Painting and Wall Coverings for Multi-Family Apartment Building 2.3 at Westlawn Gardens Phase 2; and, be it

 

FURTHER RESOLVED, that funds for these services will come from Westlawn Renaissance III LLC; and, be it

 

FURTHER RESOLVED, that the proper officers of Travaux Inc. be and hereby are authorized and directed to properly execute said contract for and on behalf of Travaux Inc.; and, be it

 

FURTHER RESOLVED, that if any extensions of the time of performance are needed the officers of Travaux Inc. may approve such request without any further action of the Board of Directors Travaux Inc.; and, be it

 

FURTHER RESOLVED, that all of above is contingent upon receiving the approval of the U.S. Department of Housing and Urban Development, if required; and, be it

 

FURTHER RESOLVED, that all acts previously performed relative to this matter by the Board of Directors of Travaux Inc. and the officers of Travaux Inc. be and hereby are approved, ratified, and confirmed in all respects.

 

Requestor

 

Drafter

Modernization & Development, November 7, 2018