Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $1,351,000 for a total estimated cost of these projects being $1,607,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Cover Letter, 2. Hearing Notice List, 3. Fiscal note
Number
090013
Version
SUBSTITUTE 1
Reference
081268
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $1,351,000 for a total estimated cost of these projects being $1,607,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $1,351,000. The total estimated cost of these projects is $1,607,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

2nd, 5th and 9th Aldermanic Districts

N. 92nd St./N. 91st St. - W. Capitol Dr. to W. Good Hope Rd. (SM493090101) File Number 081268: Converting grass medians into bioretention facilities. (Nonassessable Sewer Fund -- $750,000 TSS Reduction Fund). The total estimated cost for this project including the requested amount is $780,000. This project is anticipated to be completed during the 2009 construction season.

12th Aldermanic District

S. 14th St. - W. Hayes Ave. to W. Harrison Ave. (SM495070027) File Number 081392: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $35,000 Additional Funds). The total estimated cost for this project including the requested amount is $241,000. This project is anticipated to be completed during the 2009 construction season.

15th Aldermanic District

Alley between W. Brown St., W. Lloyd St., N. 23rd St., and N. 24th St. (TD06584008) File Number 051275: Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches...

Click here for full text