File #: 180516    Version:
Type: Resolution Status: Passed
File created: 7/10/2018 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 7/31/2018
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $723,200 for a total estimated cost of $786,200.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. Official Notice.pdf, 2. Signed Letter.pdf, 3. Notice Published on 8-16-18 180516
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
8/9/20181 MAYOR SIGNED   Action details Meeting details Not available
7/31/20181 COMMON COUNCIL ADOPTED

Minutes note: Ald. Coggs moved to return to Public Works Committee: N. 2nd St. -- W. North Ave. to W. Center St. (ST211140116) File Number 120112: Concrete pavement reconstruction, replace all curb and gutter, sidewalk and driveway approaches, narrow the roadway from 40 feet to 36 feet, sodding ( 12’ width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $100,000; Nonassessable Reconstruction Paving Fund --$300,000). The total estimated cost for this project including the requested amount is $470,000. This project is anticipated to be completed during the 2019 construction season.
Pass14:0 Action details Meeting details Not available
7/18/20181 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski - DPW 2nd Aldermanic District N. 64th St. -- W. Hampton Ave. to W. Villard Ave. (ST211180226). Install traffic calming speed hump(s). Ald. Johnson stated he’s in support. Ald. Borkowski moved approval. (Prevailed 4-0) 5th Aldermanic District W. Metcalf Pl.-N. 97th St. to N. 100th St. (ST211180120). Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (9’ width of tree border area), and grading. Ald. Donovan moved approval. (Prevailed 4-0) 6th Aldermanic District N. 2nd St. -- W. North Ave. to W. Center St. (ST211140116). Concrete pavement reconstruction, replace all curb and gutter, sidewalk and driveway approaches, narrow the roadway from 40 feet to 36 feet, sodding ( 12’ width of tree border area), and grading. Cole Knueppel 2350 N 2nd St stated he is concerned about the street being narrowed. Allen Roberts 2648 N 2nd St stated there are distressed properties on the street and he is against the project. Sharon Abston Coleman 2358 N 2nd St stated she is concerned about narrowing the street. Troy Yancy 2600 N 2nd St stated parking on the street was disrupted earlier this year for a sewer project and she doesn’t want the same disruption during this project. Ald. Kovac moved approval. (Prevailed 5-0) N. 16th St. -- W. Burleigh St. to W. Ring St. (ST211180156). Install traffic calming speed hump(s). Fred Barnes 1532 W Burleigh St stated he is opposed to the speed humps. Alfonso Bryant 3180 N 16th St stated he wants two speed humps instead of one. Ald. Kovac moved approval. (Prevailed 5-0) 7th Aldermanic District N. 39th St. -- W. Roosevelt Dr. to W. Fiebrantz Av. (ST211180223). Install traffic calming speed hump(s). Ald. Donovan moved approval. (Prevailed 5-0) 10th Aldermanic District N. 58th St. -- W. Brooklyn Pl. to W. Townsend St. (ST211180225). Install traffic calming speed hump(s). Peggy Bartel 3335 N 58th St stated she is opposed to the speed hump. Ald. Murphy moved to delete the project. (Prevailed 5-0) 13th Aldermanic District W. Eden Pl. -- S. 8th St. to S. 11th St. (Including S. 8th St., S. 9th Pl., S. 11th St. and W. Morgan Pl.) (ST211150136). Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding ( 4’ width of tree border area), and grading. Ald. Kovac moved approval. (Prevailed 5-0) Ald. Borkowski moved approval as amended. (Prevailed 5-0)
Pass5:0 Action details Meeting details Video Video
7/13/20180 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/10/20180 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
180516
Version
SUBSTITUTE 2
Reference
120112
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $723,200 for a total estimated cost of $786,200.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $723,200. The total estimated cost of these projects is $786,200.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

2nd Aldermanic District

N. 64th St. -- W. Hampton Ave. to W. Villard Ave. (ST211180226). Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $27,500; Nonassessable Reconstruction Paving Fund -- $500). The total estimated cost for this project including the requested amount is $28,000. This project is anticipated to be completed during the 2018 construction season.

5th Aldermanic District

W. Metcalf Pl.-N. 97th St. to N. 100th St. (ST211180120). File Number 170391: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding ( 9’ width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $17,000; Nonassessable Reconstruction Paving Fund -- 245,000). The total estimated cost for this project including the requested amount is $285,000. This project is anticipated to be completed during th...