File #: 081420    Version: 0
Type: Resolution Status: Passed
File created: 2/10/2009 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 3/3/2009
Effective date:    
Title: Resolution authorizing the proper city officials to execute amended Utility Agreements with the State of Wisconsin, Department of Transportation for work on City of Milwaukee facilities in conjunction with the North-South Mitchell Interchange with a total estimated cost of $2,769,671.33 with an estimated Grantor’s share of $2,492,704.20 and an estimated City of Milwaukee share of $276,967.13.
Sponsors: THE CHAIR
Indexes: EXPRESSWAYS, INTERGOVERNMENTAL AGREEMENTS, PUBLIC UTILITIES, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Cover Letter.pdf, 2. Fiscal Note.pdf, 3. Comptroller's Certificate, 4. Hearing Notice List, 5. Municipal Agreement Amendment No 67 & 70
Number
081420
Version
ORIGINAL
Reference
971111
Sponsor
THE CHAIR
Title
Resolution authorizing the proper city officials to execute amended Utility Agreements with the State of Wisconsin, Department of Transportation for work on City of Milwaukee facilities in conjunction with the North-South Mitchell Interchange with a total estimated cost of $2,769,671.33 with an estimated Grantor’s share of $2,492,704.20 and an estimated City of Milwaukee share of $276,967.13.
Analysis
This resolution authorizes the Commissioner of Public Works and the Comptroller to execute the amended Utility Agreements Nos. 67 and 70 for Milwaukee Water Works and Environmental Engineering for the utility work in conjunction with the North-South Mitchell Interchange (NSMI), (2009 Advanced Utilities Contract at Mallory Avenue and Layton Avenue), with a total estimated cost of $2,769,671.33 with an estimated Grantor’s share of $2,492,704.20 and an estimated City of Milwaukee share of $276,967.13.
Body
Whereas, The State of Wisconsin, Department of Transportation (WISDOT) scheduled the rehabilitation of the North-South Mitchell Interchange (NMSI) in the City of Milwaukee; and

Whereas, The Department of Public Works (DPW) has worked with the WISDOT over the past year in planning the design and construction phasing of the project to best meet the needs of the citizens of the City of Milwaukee (CITY) and of the region as a whole; and

Whereas, Work on the NSMI has been phased in four major phases, being Phase I (South 27th Street; Airport Spur I; West Grange Avenue; West College Avenue) scheduled for 2009, Phase II (North Leg; West Layton Avenue; Airport Spur II) scheduled for 2010, and Phases III & IV (Mitchell Interchange) scheduled for 2011 and 2012; and

Whereas, There will be substantial work required on CITY utilities as a result of the design and construction associated with these NSMI contracts; and

Whereas, Wisconsin Statute 84.295(4m) indicates that the WISDOT will pay 90 pe...