powered help
header-left header-center header-right
File #: 081268    Version:
Type: Resolution Status: Passed
File created: 1/16/2009 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 2/10/2009
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $700,000 for a total estimated cost of these projects being $3,918,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Cover Letter, 2. Hearing Notice List, 3. Fiscal Note
Number
081268
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $700,000 for a total estimated cost of these projects being $3,918,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $700,000 with the total cost estimated to be $3,918,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

2nd, 5th & 9th Aldermanic Districts

N. 92nd St./N. 91st St. - W. Capitol Dr. to W. Good Hope Rd. (SM493090101): Storm rehabilitation. (Converting grass medians into bioretention facilities). (Nonassessable Sewer Maintenance Fund -- $30,000 TSS Reduction Fund). The total estimated cost for this project including the requested amount is $500,000. This project is anticipated to be completed during the 2009 construction season.

10th Aldermanic District

W. Burleigh St. - N. 57th St. to N. 58th St. (SM495080072): Relaying sanitary sewer. The total estimated cost for this project is $68,000. This project is anticipated to be completed during the 2009 construction season.

11th Aldermanic District

Area bounded by W. Wilbur Ave., W. Howard Ave., S. 51st St., and S. 53rd St. (SM495090002): Sanitary sewer exams. The total estimated cost for this project is $50,000. This project is anticipated to be completed during the 2009 construction season.

13th Aldermanic District

S. 6th St. - W. Grange Ave. to W. Ramsey Ave. (Ext’d) (SW172080103): County project. Relocating existin...

Click here for full text