Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $11,533,590 for a total estimated cost of these projects being $13,001,970.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $11,533,590. The total estimated cost of these projects is $13,001,970.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
1st Aldermanic District
Alleys between W. Hope Ave.(SE 251), W. Roosevelt Dr., N. 27th St., and N. 30th St. (east of N. 28th St. to N. 30th St. of the southerly east-west legs) (SM495150100) File Number 151137: Storm sewer lining and repair. (Nonassessable Sewer Maintenance Relay Fund -- $38,000). The total estimated cost for this project including the requested amount is $50,000. This project is anticipated to be completed during the 2017 construction season.
N. 28th St. - Alley north of W. Hope Ave. (SE 251) to alley south of W. Roosevelt Dr. (SM495160016) File Number 151521: Relaying storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $109,000). The total estimated cost for this project including the requested amount is $121,000. This project is anticipated to be completed during the 2017 construction season.
N. 29th St. - Alley north of W. Hope Ave. (SE 251) to alley south of W. Roosevelt Dr. (SM495160017) File Number 151521: Relaying storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $114,000). The total estimated cost for this project including the requested amount is $126,000. This project is anticipated to be completed during the 2017 construction season.
2nd Aldermanic District
W. Armitage Ave. - W. Leon Tr. to W. Fond du Lac Ave. (WT410170619) File Number 151521: Relaying water main. (Nonassessable Water Fund Budget Line 6410 -- $75,000). The total estimated cost for this project including the requested amount is $90,000. This project is anticipated to be completed during the 2017 construction season.
W. Leon Tr. - N. 60th St. to W. Armitage Ave. (WT410170618) File Number 151521: Relaying water main. (Nonassessable Water Fund Budget Line 6410 -- $550,000). The total estimated cost for this project including the requested amount is $580,000. This project is anticipated to be completed during the 2017 construction season.
N. 70th St. - W. Glendale Ave. to W. Hampton Ave. (WT410170684) File Number 151848: Relaying water main. (Nonassessable Water Fund Budget Line 6410 -- $460,000). The total estimated cost for this project including the requested amount is $485,000. This project is anticipated to be completed during the 2017 construction season.
N. 71st St. - W. Glendale Ave. to W. Courtland Ave. (WT410170685) File Number 151848: Relaying water main. (Nonassessable Water Fund Budget Line 6410 -- $240,000). The total estimated cost for this project including the requested amount is $255,000. This project is anticipated to be completed during the 2017 construction season.
3rd Aldermanic District
N. Newhall St. - 200 feet m/l north of E. Bradford Ave. to E. Webster Pl. (SM495150021) File Number 141727: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $59,000). The total estimated cost for this project including the requested amount is $74,000. This project is anticipated to be completed during the 2017 construction season.
E. Webster Pl. - N. Newhall St. to N. Bartlett Ave. (SM495150022) File Number 141727: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $92,000). The total estimated cost for this project including the requested amount is $107,000. This project is anticipated to be completed during the 2017 construction season.
4th Aldermanic District
W. Wells St. (USH 18) bridge over the Milwaukee River (B-40-544) (BR320130101) (2195-03-00) File Number 141834: Rehabilitate bridge including hydraulic, mechanical and electrical upgrades; and placement of concrete approach slabs.
Grantor Non-Reimbursable Structure Fund -- $5,785,000
Grantor Reimbursable Structure Fund -- $75,000
City Share Non-assessable Structure Fund -- $25,000
These funds are to be transferred to the construction account BR3201301XX (2195-03-70)
Previously authorized for project construction: $0.00
Current estimated cost of total project including this resolution: $6,637,500
Original estimated cost of the project: (Resolution 121291): $3,876,250
This project is anticipated to be completed during the 2018 construction season.
N. 25th St. - W. Wisconsin Ave. to W. Wells St. (SM495170030) File Number 170019: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $125,000). The total estimated cost for this project including the requested amount is $137,000. This project is anticipated to be completed during the 2017 construction season.
N. 29th St. - W. Michigan St. to W. Wisconsin Ave. (SM495170028) File Number 170019: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $141,000). The total estimated cost for this project including the requested amount is $153,000. This project is anticipated to be completed during the 2017 construction season.
4th and 10th Aldermanic Districts
N. 35th St. - W. Clybourn St. to W. Wisconsin Ave. (SM495170029) File Number 170019: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $257,000). The total estimated cost for this project including the requested amount is $269,000. This project is anticipated to be completed during the 2017 construction season.
6th Aldermanic District
E. North Ave. at N. Palmer St. and at N. Buffum St. (ST211170194) File Number 161694: Install traffic calming devices - curb push outs. (Nonassessable Reconstruction Paving Fund -- $60,000). The total estimated cost for this project including the requested amount is $70,000. This project is anticipated to be completed during the 2017 construction season.
7th Aldermanic District
W. Ely Pl./N. 54th St. - W. Fond du Lac Ave. to W. Congress St. (SM495160058) File Number 160263: Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $54,000). The total estimated cost for this project including the requested amount is $64,000. This project is anticipated to be completed during the 2017 construction season.
N. 54th St. - W. Glendale Ave. (WE 657) to 454 feet south of W. Hampton Ave. (WT410170671) File Number 151848: Relaying water main. (Nonassessable Water Fund Budget Line 6410 -- $270,000). The total estimated cost for this project including the requested amount is $285,000. This project is anticipated to be completed during the 2017 construction season.
11th Aldermanic District
West Oklahoma Avenue Bioswales: W. Oklahoma Ave. - S. 49th St. to S. 60th St. (SM499170100) File Number 161562: (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $110,000). The total estimated cost for this project including the requested amount is $125,000. This project is anticipated to be completed during the 2018 construction season.
13th Aldermanic District
System 2413 Outfall - 350 feet east of S. 20th St. to the Kinnickinnic River (SM499170108) File Number 170479: (Nonassessable Storm Water Quality Fund -- $29,000). The total estimated cost for this project including the requested amount is $39,000. This project is anticipated to be completed during the 2017 construction season.
14th Aldermanic District
S. Howell Ave. at E. Montana St. (south) and at E. Dewey Pl. (ST211170197) File Number 170142: Install traffic calming devices - curb push outs. (Nonassessable Reconstruction Paving Fund -- $105,000). The total estimated cost for this project including the requested amount is $120,000. This project is anticipated to be completed during the 2017 construction season.
15th Aldermanic District
W. Brown St. Bridge over CP RR (3000W) (BR320141301/ST320141301) (2984-06-06) File Number 140427: Replace bridge, abutments and approach roadways.
Grantor Non-Reimbursable Paving Fund -- $130,435
Grantor Reimbursable Paving Fund -- $19,565
City Share Non-assessable Paving Fund -- $16,750
These funds are to be transferred to the construction account ST3201413XX (2984-06-06)
Grantor Non-Reimbursable Structure Fund -- $1,688,410
Grantor Reimbursable Structure Fund -- $253,260
City Share Non-assessable Structure Fund -- $506,170
These funds are to be transferred to the construction account BR3201413XX (2984-06-06)
Previously authorized for project construction: $0.00
Current estimated cost of total project including this resolution: $3,046,470
Original estimated cost of the project: (Resolution 140427): $3,046,470
This project is anticipated to be completed during the 2018 construction season.
N. 34th St. - W. Garfield Ave. to W. North Ave. (SM495160092) File Number 161295: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $109,000). The total estimated cost for this project including the requested amount is $121,000. This project is anticipated to be completed during the 2017 construction season.
N. 48th St. - W. Meinecke Ave. to W. Wright St. (SM495160003) File Number 151288: Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $37,000). The total estimated cost for this project including the requested amount is $47,000. This project is anticipated to be completed during the 2017 construction season.
now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
Mary Dziewiontkoski/Jean Ziller
Nfr 15