Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $84,000 with the total cost estimated to be $766,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:
2nd and 9th Aldermanic District
West Mill Road Bioswales: W. Mill Rd. - N. 43rd St. to N. 91st St. (SM499160121): (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $15,000, Additional Funds). The total estimated cost for this project including the requested amount is $400,000. This project is anticipated to be completed during the 2017 construction season.
4th Aldermanic District
E./W. Wells St. - N. Broadway to N. 6th St. (WT410180009): Hydrant alterations. (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $13,000). The total estimated cost for this project including the requested amount is $40,000. This project is anticipated to be completed during the 2018 construction season.
7th Aldermanic District
N. 35th St. - 200 feet south of W. Capitol Dr. to W. Capitol Dr. (SM494170014): Relaying sanitary sewer. (Infiltration/Inflow Reduction Fund -- $ 12,000). The total estimated cost for this project including the requested amount is $91,000. This project is anticipated to be completed during the 2018 construction season.
11th Aldermanic District
W. Cleveland Ave. - W. Kinnickinnic River Pkwy. to S. 67th St. (SM495170048): Sanitary Sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost for this project including the requested amount is $112,000. This project is anticipated to be completed during the 2018 construction season.
13th Aldermanic District
System 2413 Outfall - 350 feet east of S. 20th St. to The Kinnickinnic River (SM499170108): (Nonassessable Storm Water Quality Fund -- $10,000). The total estimated cost for this project including the requested amount is $39,000. This project is anticipated to be completed during the 2017 construction season.
15th Aldermanic District
N. Sherman Bd. (east side) - W. Wright St. to W. Clarke St. (SM495170049): Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $10,000). The total estimated cost for this project including the requested amount is $49,000. This project is anticipated to be completed during the 2018 construction season.
N. 18th St. - 115 feet south of W. Galena St. to W. Galena St. (SM495170050): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000). The total estimated cost for this project including the requested amount is $35,000. This project is anticipated to be completed during the 2018 construction season.
;and, be it
Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
Mary Dziewiontkoski/Jean Ziller
Npr 15