powered help
header-left header-center header-right
File #: 170278    Version:
Type: Resolution Status: Passed
File created: 5/31/2017 In control: COMMON COUNCIL
On agenda: Final action: 6/20/2017
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $164,000 for a total estimated cost of these projects being $2,312,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
170278
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $164,000 for a total estimated cost of these projects being $2,312,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $164,000 with the total cost estimated to be $2,312,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

1st and 7th Aldermanic Districts

W. Capitol Dr. - 335 feet m/l east of N. 34th St. to N. 35th St. (SM494170010): Relaying sanitary sewer. (Infiltration/Inflow Reduction Fund -- $12,000). The total estimated cost for this project including the requested amount is $152,000. This project is anticipated to be completed during the 2018 construction season.

4th Aldermanic District

N. 33rd St. - W. Clybourn St. to 250 feet north of W. St. Paul Ave. (SM495170037): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000). The total estimated cost for this project including the requested amount is $53,000. This project is anticipated to be completed during the 2018 construction season.

6th Aldermanic District

N. 5th St. - N. Dr. Martin Luther King Jr. Dr. to W. Keefe Ave. (SM495170039): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $300,000. This project is anticipated to be completed during the 2018 construction season.

7th Alde...

Click here for full text