powered help
header-left header-center header-right
File #: 160798    Version:
Type: Resolution Status: Passed
File created: 10/11/2016 In control: COMMON COUNCIL
On agenda: Final action: 11/1/2016
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $5,475,000 for a total estimated cost of these projects being $6,179,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number

160798

Version

Substitute 1

Reference

151521

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $5,475,000 for a total estimated cost of these projects being $6,179,000.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $5,475,000.  The total estimated cost of these projects is $6,179,000.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

2nd Aldermanic District

 

N. 62nd St. - W. Fiebrantz Ave. to W. Congress St. (WT410160902) File Number 151521:  Relaying water main.  (Nonassessable Water Fund Budget Line 6410 -- $630,000).  The total estimated cost for this project including the requested amount is $665,000.  This project is anticipated to be completed during the 2017 construction season.

 

N. 64th St. - W. Capitol Dr. to W. Hope Ave. (WT410160904) File Number 151521:  Relaying water main.  (Nonassessable Water Fund Budget Line 6410 -- $465,000).  The total estimated cost for this project including the requested amount is $505,000.  This project is anticipated to be completed during the 2017 construction season.

 

N. 66th St. - W. Fiebrantz Ave. to W. Congress St. (WT410160903) File Number 151521:  Relaying water main.  (Nonassessable Water Fund Budget Line 6410 -- $965,000).  The total estimated cost for this project including the requested amount is $1,000,000.  This project is anticipated to be completed during the 2017 construction season.

 

N. 76th St. - 110 feet north of W. Leon Terr. To 140 feet north of W. Sheridan Ave. (SM495160031) File Number 151746:  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $181,000).  The total estimated cost for this project including the requested amount is $196,000.  This project is anticipated to be completed during the 2016-2017 construction season.

 

2nd and 9th Aldermanic Districts

 

North 91st Street Bioswales:  N. 91st St. - W. Mill Rd. to W. Good Hope Rd. (SM499160107) File Number 151521:  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $90,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2017 construction season.

 

3rd Aldermanic District

 

N. Humboldt Blvd. at E. Center St. (ST211160177) File Number 160263:  Install pedestrian access ramps.  (Nonassessable Reconstruction Paving Fund -- $15,000, Additional funds).  The total estimated cost for this project including the requested amount is $31,000.  This project is anticipated to be completed during the 2017 construction season.

 

4th Aldermanic District

 

West Highland Avenue Bioswales:  W. Highland Ave. - N. 12th St. to N. 27th St. (SM499160105) File Number 160425:  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $79,000, Additional Funds).  The total estimated cost for this project including the requested amount is $400,000.  This project is anticipated to be completed during the 2017 construction season.

 

5th Aldermanic District

 

W. Marion St. - N. 85th St. to N. 86th St. (WT410160905) File Number 151521:  Relaying water main.  (Nonassessable Water Fund Budget Line 6410 -- $90,000).  The total estimated cost for this project including the requested amount is $105,000.  This project is anticipated to be completed during the 2017 construction season.

 

W. Marion St. - N. 87th St. to N. 90th St. (WT410160906) File Number 151521:  Relaying water main.  (Nonassessable Water Fund Budget Line 6410 -- $250,000).  The total estimated cost for this project including the requested amount is $275,000.  This project is anticipated to be completed during the 2017 construction season.

 

North 92nd Street Bioswales:  N. 92nd St. - W. Capitol Dr. to W. Hampton Ave. (SM499160106) File Number 151521:  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $50,000).  The total estimated cost for this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2017 construction season.

 

6th Aldermanic District

 

N. 2nd St. at W. Pleasant St. (TD04188004) File Number 160696: (Intersection improvements).  (TID Nonassessable Paving Fund -- $65,000).  The total estimated cost for this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2016 construction season.

 

8th Aldermanic District

 

S. 35th St. - W. Greenfield Ave. to W. Mitchell St. (WT410160004) File Number 151547:  Hydrant alteration.  (Nonassessable Water Fund Budget Line 6410 -- $20,000, Additional Funds).  The total estimated cost for this project including the requested amount is $65,000.  This project is anticipated to be completed during the 2016-2017 construction season.

 

9th Aldermanic District

 

N. Delta Pl. - W. Calumet Rd. to W. Port Ave. (WT410160908) File Number 151521:  Relaying water main.  (Nonassessable Water Fund Budget Line 6410 -- $465,000).  The total estimated cost for this project including the requested amount is $495,000.  This project is anticipated to be completed during the 2017 construction season.

 

W. Luebbe Ln. - N. 51st Blvd. to N. Edgeworth Dr. (WT410160909) File Number 151521:  Relaying water main.  (Nonassessable Water Fund Budget Line 6410 -- $505,000).  The total estimated cost for this project including the requested amount is $540,000.  This project is anticipated to be completed during the 2017 construction season.

 

N. 59th St. - W. Calumet Rd. to W. Port Ave. (WT410160907) File Number 151521:  Relaying water main.  (Nonassessable Water Fund Budget Line 6410 -- $170,000).  The total estimated cost for this project including the requested amount is $185,000.  This project is anticipated to be completed during the 2017 construction season.

 

10th Aldermanic District

 

West Nash Street Bioswales:  W. Nash St. - W. Appleton Ave. to N. 76th St. (SM499160102) File Number 151521:  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $95,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2017 construction season.

 

10th and 15th Aldermanic Districts

 

W. Wisconsin Ave. - N. 37th St. to a point west of N. 39th St. (SM495160007) File Number 151288:  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $433,000).  The total estimated cost for this project including the requested amount is $443,000.  This project is anticipated to be completed during the 2016-2017 construction season.

 

N. 37th St. - W. Wisconsin Ave. To 175 feet north of W. Wisconsin Ave. (SM495160013) File Number 151288:  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $32,000).  The total estimated cost for this project including the requested amount is $44,000.  This project is anticipated to be completed during the 2016-2017 construction season.

 

15th Aldermanic District

 

N. 20th St. - W. North Ave. to W. Wright St. (SM495150074) File Number 150997:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $875,000).  The total estimated cost for this project including the requested amount is $895,000.  This project is anticipated to be completed during the 2016-2017 construction season.

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/Denise Reinholtz

Nfr 3

10/14/2016