File #: 160589    Version:
Type: Resolution Status: Passed
File created: 9/1/2016 In control: COMMON COUNCIL
On agenda: Final action: 9/20/2016
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $188,000 for a total estimated cost of these projects being $7,294,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
9/28/20161 MAYOR SIGNED   Action details Meeting details Not available
9/20/20161 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Video Video
9/7/20160 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Proposed Substitute A
Pass4:0 Action details Meeting details Video Video
9/7/20161 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski - Department of Public Works
Pass4:0 Action details Meeting details Not available
9/1/20160 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

160589

Version

Substitute 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $188,000 for a total estimated cost of these projects being $7,294,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $188,000 with the total cost estimated to be $7,294,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

4th Aldermanic District

 

N. 16th St. (extended) - W. State St. to W. Highland Ave. (SM495160068):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $87,000.  This project is anticipated to be completed during the 2017 construction season.

 

4th, 6th, and 7th Aldermanic Districts

 

Various Locations in System 3016 (SM495160069):  Sewer examinations by contract.  (Nonassessable Sewer Maintenance Relay Fund -- $20,000).  The total estimated cost for this project including the requested amount is $530,000.  This project is anticipated to be completed during the 2017 construction season.

 

6th Aldermanic District

 

W. Groeling Ave. - N. 14th St. to N. Teutonia Ave. (SM495160071):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $126,000.  This project is anticipated to be completed during the 2017 construction season.

 

N. 14th St. - W. Locust St. to W. Groeling Ave. (SM495160070):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $79,000.  This project is anticipated to be completed during the 2017 construction season.

 

8th Aldermanic District

 

S. 31st St. - W. Madison St. to W. Greenfield Ave. (SM495160072):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $56,000.  This project is anticipated to be completed during the 2017 construction season.

 

11th Aldermanic District

 

S. 60th St. - W. Cold Spring Rd. to W. Morgan Ave. (WT410170006):  Hydrant alteration.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2017 construction season.

 

12th Aldermanic District

 

S. 18th St. - W. Scott St. to W. Greenfield Ave. (SM495160073):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $197,000.  This project is anticipated to be completed during the 2017 construction season.

 

Windlake Avenue Bioswale Project:  S. 19th St. at W. Windlake Ave. (SM499160114):  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $1,000).  The total estimated cost for this project including the requested amount is $50,000.  This project is anticipated to be completed during the 2016 construction season.

 

13th Aldermanic District

 

Building Sanitary Sewer Lateral Lining in an area bounded by W. Layton Ave. to W. Edgerton Ave. from S. 20th St. to S. 27th St. (SM494160201):  Sanitary sewer lining.

(Infiltration/Inflow Reduction Fund -- $50,000).  The total estimated cost for this project including the requested amount is $2,626,000.  This project is anticipated to be completed during the 2017 construction season.

 

13th and 14th Aldermanic Districts

 

Area bounded by W. Oklahoma Ave. to E. Bottsford Ave. from S. 13th St. to S. Kansas Ave. (SM494160202):  Sanitary sewer lining.  (Infiltration/Inflow Reduction Fund -- $25,000).  The total estimated cost for this project including the requested amount is $2,785,000.  This project is anticipated to be completed during the 2017 construction season.

 

15th Aldermanic District

 

N. 20th St. - W. Brown St. to 115 feet south of W. Garfield Ave. (SM495160074):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $483,000.  This project is anticipated to be completed during the 2016 construction season.

 

City Wide

 

Bioretention Maintenance Contract (SM499160117):  Stormwater Quality projects to meet TMDL requirements. (Nonassessable Storm Water Quality Fund --$1,000).

The total estimated cost for this project including the requested amount is $175,000.  This project is anticipated to be completed during the 2016 construction season.

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 