Title: Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $141,000 for a total estimated cost of these projects being $1,746,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
9/28/20161 MAYOR SIGNED   Action details Meeting details Not available
9/20/20161 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Video Video
9/7/20160 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Proposed Substitute A
Pass4:0 Action details Meeting details Video Video
9/7/20161 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski - Department of Public Works
Pass4:0 Action details Meeting details Not available
9/1/20160 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

 

Number

160587

Version

Substitute 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $141,000 for a total estimated cost of these projects being $1,746,000.

Analysis

This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed.  After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable.  A resolution will be submitted after the Public Hearing authorizing construction.  The City cost for engineering these projects is estimated to be $141,000 with the total cost estimated to be $1,746,000.

Body

Resolved, By the Common Council of the City of Milwaukee that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:

 

1st Aldermanic District

 

N. 49th St. - W. Villard Ave. to W. Custer Ave. (ST211180105):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $20,000).  The total estimated cost for this project including the requested amount is $220,000.  This project is anticipated to be completed during the 2018 construction season.

 

2nd Aldermanic District

 

N. 73rd St. - W. Capitol Dr. to W. Congress St. (ST211180107):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $25,000).  The total estimated cost for this project including the requested amount is $445,000.  This project is anticipated to be completed during the 2018 construction season.

 

N. 87th St. - W. Silver Spring Dr. to W. Fond du Lac Ave. (ST211150112):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $8,000, Additional Funds).  The total estimated cost for this project including the requested amount is $230,000.  This project is anticipated to be completed during the 2018 construction season.

 

5th Aldermanic District

 

N. 80th St. - W. Townsend St. to W. Keefe Ave. (Including N. Walton Pl. - W. Lisbon Ave. to W. Townsend St.) (ST211180108):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $15,000).  The total estimated cost for this project including the requested amount is $88,000.  This project is anticipated to be completed during the 2018 construction season.

 

N. 85th St. - W. Locust St. to W. Burleigh St. (ST211150169):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $8,000, Additional Funds).  The total estimated cost for this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2018 construction season.

 

7th Aldermanic District

 

N. 38th St. - N. Elmhurst Rd. to N. Montreal St. (ST211180103):  Paving the roadway with concrete.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading to said work.  (Nonassessable Reconstruction Paving Fund -- $15,000).  The total estimated cost for this project including the requested amount is $95,000.  This project is anticipated to be completed during the 2018 construction season.

 

11th Aldermanic District

 

S. 54th St. - W. Midland Dr. to W. Forest Home Ave. (ST211180106):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $20,000).  The total estimated cost for this project including the requested amount is $190,000.  This project is anticipated to be completed during the 2018 construction season.

 

14th Aldermanic District

 

S. Lenox Ave. - E. Wilbur Ave. to E. Saveland Ave. (SM495160067):  Installing new storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $108,000.  This project is anticipated to be completed during the 2016 construction season.

 

15th Aldermanic District

 

N. 41st St. - W. Meinecke Ave. to W. Wright St. (ST211180104):  Paving the roadway with concrete.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading to said work.  (Nonassessable Reconstruction Paving Fund -- $20,000).  The total estimated cost for this project including the requested amount is $205,000.  This project is anticipated to be completed during the 2018 construction season.

 

; and, be it

 

Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it

 

Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/Denise Reinholtz

Apr 1