powered help
header-left header-center header-right
File #: 080910    Version:
Type: Resolution Status: Passed
File created: 10/29/2008 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 12/16/2008
Effective date:    
Title: Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $116,000 for a total estimated cost of these projects being $1,155,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Cover Letter, 2. Fiscal note, 3. Hearing notice list

Number

080910

Version

SUBSTITUTE 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $116,000 for a total estimated cost of these projects being $1,155,000.

Analysis

This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed.  After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable.  A resolution will be submitted after the Public Hearing authorizing construction.  The City cost for engineering these projects is estimated to be $116,000 with the total cost estimated to be $1,155,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:

 

5th Aldermanic District

 

W. Chambers St. - N. 90th St. to N. 92nd St. (ST211100104): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $10,000).  The total estimated cost for this project including the requested amount is $95,000.  This project is anticipated to be completed during the 2010 construction season.

 

N. 93rd St. - W. Elmore Ave. to W. Melvina St. (including N. Willis Pl. - W. Lisbon Ave. to W. Elmore Ave. and W. Elmore Ct.) (ST211060110): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $3,000 Additional Funds.) File Number 051444 authorized $15,400.  Total engineering cost is $18,400.  The total estimated cost for this project including the requested amount is $137,000.  This project is anticipated to be completed during the 2009 construction season.

 

8th Aldermanic District

 

W. Hayes Ave. - S. 27th St. to S. 29th St. (ST211100106): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $8,000).  The total estimated cost for this project including the requested amount is $85,000.  This project is anticipated to be completed during the 2010 construction season.

 

S. 38th St. - W. Greenfield Ave. to W. National Ave. (Portions in the City of West Milwaukee) (ST211060154) File Number 071381: Asphalt pavement resurfacing, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, grading, and tree removal where necessary. (Nonassessable Reconstruction Paving Fund -- $45,000 Additional Funds).  The total estimated cost for this project including the requested amount is $320,000.  This project is anticipated to be completed during the 2009 construction season.

 

11th Aldermanic District

 

W. Crawford Ave. - S. 84th St. to S. 92nd St. (ST211090107): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $10,000 Additional Funds). File No. 071168 authorized $18,000.  Total engineering cost is $28,000.  The total estimated cost for this project including the requested amount is $144,000.  This project is anticipated to be completed during the 2009 construction season.

 

W. Eden Pl. - S. 77th St. to S. 79th St. (ST211100105): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $10,000).  The total estimated cost for this project including the requested amount is $104,000.  This project is anticipated to be completed during the 2010 construction season.

 

S. 63rd St. - W. Eden Pl. to W. Morgan Ave. (ST211100102): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $45,000.  This project is anticipated to be completed during the 2010 construction season.

 

S. 77th St. - W. Warnimont Ave. to W. Eden Pl. (ST211100103): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000).  The total estimated cost for this project including the requested amount is $45,000.  This project is anticipated to be completed during the 2010 construction season.

 

13th Aldermanic District

 

S. 1st St. - A point 170 feet m/l south of W. Armour Ave. to a point 160 feet m/l north of W. Allerton Ave. (ST211100101): Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $10,000).  The total estimated cost for this project including the requested amount is $145,000.  This project is anticipated to be completed during the 2010 construction season.

 

Various Aldermanic Districts

 

Various Locations (ST212080001): Administration cost for alley paving engineering. (Nonassessable Alley Paving Fund-2008 Budgeted Funds - $10,000 Additional Funds). File Number 071055 authorized $25,000.  The total estimated cost for this project including the requested amount is $35,000.  This project is anticipated to be completed in 2008.

 

; and, be it

 

Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it

 

Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

MLD:dr

Apr 5

11/26/08