File #: 151645    Version:
Type: Resolution Status: Passed
File created: 3/1/2016 In control: COMMON COUNCIL
On agenda: Final action: 3/29/2016
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $5,510,293 for a total estimated cost of $6,502,515.39.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. Cover Letter, 2. Official Notice, 3. Cap. Grant Cert. Res. 151645- N 27th St.pdf, 4. Cap. Grant Cert. Res. 151645- N 60th St.pdf, 5. Notice Published on 4-14-16
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
4/14/20161 CITY CLERK PUBLISHED   Action details Meeting details Not available
4/6/20161 MAYOR SIGNED   Action details Meeting details Not available
3/29/20161 COMMON COUNCIL ADOPTEDPass14:0 Action details Meeting details Not available
3/16/20161 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkowski - Department of Public Works 4th and 15th Aldermanic Districts N. 27th St. - W. Highland Ave. to W. Lisbon Ave. (ST320141101): Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches as necessary, sodding (5 -10 foot tree border) and grading. Ald. Bohl moved approval. (Prevailed 3-0) 9th Aldermanic District N. 60th St. - W. Florist Ave. to W. Mill Rd. (ST320140601): Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches as necessary, sodding and (4 - 6 foot tree border) and grading Ald. Puente moved approval. (Prevailed 3-0) Ald. Puente moved approval as amended. (Prevailed 3-0)
Pass3:0 Action details Meeting details Video Video
3/1/20160 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
151645
Version
SUBSTITUTE 1
Reference
140427
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $5,510,293 for a total estimated cost of $6,502,515.39.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $5,510,293. The total estimated cost of these projects is $6,502,515.39.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

4th and 15th Aldermanic Districts

N. 27th St. - W. Highland Ave. to W. Lisbon Ave. (ST320141101) (2265-00-04) File Number 140427: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches as necessary, sodding (5 -10 foot tree border), and grading.

Grantor Non-Reimbursable Paving Fund -- $2,023,304
Grantor reimbursable Paving Fund -- $50,000
City non assessable Paving Fund -- $949,299
City Assessable Paving Fund -- $5,300

These funds are to be transferred to the construction account (ST3201411XX) (2265-00-74)

Previously authorized for construction: $0.00
Current estimated cost of total project including this resolution: $3,559,145.39
Original estimated cost of the project (Res. No. 140427): $3,176,290.00

This project is anticipated to be completed during the 2016 construction season.


9th Aldermanic District

N. 60th St. - W. Florist A...