Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,494,965 for a total estimated cost of $3,084,405.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. Cover Letter, 2. Official Notice, 3. Comptrollers Certificate, 4. Cover Letter AFR 8.pdf, 5. Dist 4 e-mail, 6. Notice Published on 3-17-16
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
3/17/20161 CITY CLERK PUBLISHED   Action details Meeting details Not available
3/8/20161 MAYOR SIGNED   Action details Meeting details Not available
3/1/20161 COMMON COUNCIL ADOPTEDPass12:0 Action details Meeting details Video Video
2/17/20161 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski - Department of Public Works 3rd Aldermanic District N. Maryland Ave. - E. Newberry Blvd. to Kenwood Blvd. (ST211160106): Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (11-foot width of tree border area), and grading. Ald. Kovac stated there has been overwhelming support. Ald. Bohl moved approval. (Prevailed 3-0) 4th Aldermanic District W. Juneau Ave. - N. 17th St. to N. 20th St. (ST211160115): Install traffic calming speed hump(s). Ald. Puente moved approval. (Prevailed 3-0) W. Mt. Vernon Ave. - N. 31st St. to N. 32nd St. (ST211160123): Install traffic calming speed hump(s). Ald. Bohl moved approval. (Prevailed 3-0) N. 18th St. - W. Highland Ave. to W. Vliet St. (ST211160114): Install traffic calming speed hump(s). Ald. Puente moved approval. (Prevailed 3-0) 7th Aldermanic District W. Hope Ave./W. Maxwell Pl. - N. 51st Blvd. to W. Fond du Lac Ave. (TD04284001A): Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (6-foot width of tree border area), and grading. Ald. Puente moved approval. (Prevailed 3-0) 8th Aldermanic District S. 33rd St. - W. Scott St. to W. National Ave. (ST211160124): Install traffic calming speed hump(s). Ald. Bohl moved approval. (Prevailed 3-0) 12th Aldermanic District S. 8th St. - W. Rogers St. to W. Burnham St. (ST211160116): Install traffic calming speed hump(s). Ald. Puente moved approval. (Prevailed 3-0) S. 13th St. - W. Windlake Ave. to W. Forest Home Ave. (ST320120601): Concrete pavement reconstruction, widening from 40 feet to 48 feet, replace all curb and gutter, sidewalk and driveway approaches, tree removals, sodding and grading, no tree border, street lighting and underground communication conduits and signals. Ald. Bohl moved approval. (Prevailed 3-0)
Pass3:0 Action details Meeting details Video Video
2/12/20160 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
2/9/20160 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

151520

Version

SUBSTITUTE 1

Reference

150716

Sponsor

THE CHAIR

Title

Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,494,965 for a total estimated cost of $3,084,405.

Analysis

This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held.  The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.  The City cost of these projects approved by this resolution is estimated to be $1,494,965.  The total estimated cost of these projects is $3,084,405.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

 

3rd Aldermanic District

 

N. Maryland Ave. - E. Newberry Blvd. to Kenwood Blvd. (ST211160106) File Number 150716:  Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (11-foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $ 18,500); Nonassessable Reconstruction Paving Fund -- $275,000).  The total estimated cost for this project including the requested amount is $325,000.  This project is anticipated to be completed during the 2016 construction season.

 

4th Aldermanic District

 

W. Juneau Ave. - N. 17th St. to N. 20th St. (ST211160115):                      Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $ 6,600; Nonassessable Reconstruction Paving Fund -- $ 4,000).  The total estimated cost for this project including the requested amount is $11,000.  This project is anticipated to be completed during the 2016 construction season.

 

W. Mt. Vernon Ave. - N. 31st St. to N. 32nd St. (ST211160123): Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $ 2,800; Nonassessable Reconstruction Paving Fund -- $3,000).  The total estimated cost for this project including the requested amount is $6,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 18th St. - W. Highland Ave. to W. Vliet St. (ST211160114): Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $ 8,500; Nonassessable Reconstruction Paving Fund -- $8,000).  The total estimated cost for this project including the requested amount is $17,000.  This project is anticipated to be completed during the 2016 construction season.

 

7th Aldermanic District

 

W. Hope Ave./W. Maxwell Pl. - N. 51st Blvd. to W. Fond du Lac Ave. (TD04284001/ST211160120): Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (6-foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $11,000; Nonassessable Reconstruction Paving Fund -- $5,000; TID-42 Funds $150,000).  The total estimated cost for this project including the requested amount is $170,000.  This project is anticipated to be completed during the 2016 construction season.

 

8th Aldermanic District

 

S. 33rd St. - W. Scott St. to W. National Ave. (ST211160124): Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $ 7,700; Nonassessable Reconstruction Paving Fund -- $4,000). The total estimated cost for this project including the requested amount is $12,000.  This project is anticipated to be completed during the 2016 construction season.

 

12th Aldermanic District

 

S. 8th St. - W. Rogers St. to W. Burnham St. (ST211160116): Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $ 5,700; Nonassessable Reconstruction Paving Fund -- $2,000).  The total estimated cost for this project including the requested amount is $8,000.  This project is anticipated to be completed during the 2016 construction season.

 

S. 13th St. - W. Windlake Ave. to W. Forest Home Ave. (ST320120601) (2505-00-05) File Number 121089:  Concrete pavement reconstruction, widening from 40 feet to 48 feet, replace all curb and gutter, sidewalk and driveway approaches, tree removals, sodding and grading, no tree border, street lighting and underground communication conduits and signals.

 

Grantor Non-Reimbursable Paving Fund -- $904,560

Grantor Reimbursable Paving Fund -- $135,680

City Share Non-assessable Paving Fund -- $968,665

City Share Assessable Paving Fund -- $14,500

 

These funds are to be transferred to the construction account (ST3201206XX) (2505-00-75).

 

Previously authorized for project construction:  $0.00

 

Current estimated cost of total project including this resolution: $2,535,405

 

Original estimated cost of the project: (Resolution 111507): $1,797,300

 

This project is anticipated to be completed during the 2016 construction season.

 

; and

 

Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and

 

Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works’ Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it

 

Further Resolved, That the City Engineer and the Commissioner of Public Works are hereby authorized to negotiate and enter into an agreement with the State of Wisconsin, Department of Transportation for the City to undertake construction management duties on the following project:  S. 13th St. (ST320120601) (2505-00-05) and, be it

 

Further Resolved, That the City Engineer is authorized to approve and make periodic payments to the State of Wisconsin, Department of Transportation after receipt of invoices from said State for the city’s share of the costs for said project:  S. 13th St.  (ST320120601) (2505-00-05) and, be it

 

Further Resolved, That upon the completion of project:  S. 13th St. (ST320120601) (2505-00-05) and a determination of the actual costs, it is understood that if the City of Milwaukee’s share is less than the amount previously paid, the difference will be refunded to said City; and, be it

 

Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it

 

Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That projects: N. Maryland Ave. (ST211160106); W. Hope Ave./W. Maxwell Pl. (TD04284001/ST211160120); S. 13th St. (ST320120601) will be billed after January 1, 2018, but not before 12 months after the project contract has been completed.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/Denise Reinholtz

Afr 8

February 18, 2016