File #: 151138    Version:
Type: Resolution Status: Passed
File created: 11/24/2015 In control: COMMON COUNCIL
On agenda: Final action: 12/15/2015
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,167,500 for a total estimated cost of these projects being $3,715,500.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
12/28/20151 MAYOR SIGNED   Action details Meeting details Not available
12/15/20151 COMMON COUNCIL ADOPTEDPass14:0 Action details Meeting details Video Video
12/2/20151 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Proposed Substitute A
Pass5:0 Action details Meeting details Video Video
12/2/20151 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Individual present at the table: Mary Dziewiontkoski - Department of Public Works
Pass5:0 Action details Meeting details Not available
11/24/20150 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

151138

Version

Substitute 1

Reference

150997

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,167,500 for a total estimated cost of these projects being $3,715,500.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $3,167,500.  The total estimated cost of these projects is $3,715,500.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

4th Aldermanic District

 

W. Juneau Ave. - N. 27th St. to N. 28th St. (SM495150060) File Number 150997:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $268,000).  The total estimated cost for this project including the requested amount is $280,000.  This project is anticipated to be completed during the 2016 construction season.

 

4th and 15th Aldermanic Districts

 

N. 27th St. and W. Vliet St., N. 27th St. and W. Cherry St. (Intersections) (SM495150059) File Number 150997:  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $98,000).  The total estimated cost for this project including the requested amount is $110,000.  This project is anticipated to be completed during the 2016 construction season.

 

7th Aldermanic District

 

W. Chambers St. - N. 26th St. to N. 27th St. (SM495150042) File Number 150032:  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $48,000).  The total estimated cost for this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2016 construction season.

 

10th Aldermanic District

 

S. 73rd St. - W. Stevenson St. to W. Main St. (SM495140105) File Number 141399:  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $450,000).  The total estimated cost for this project including the requested amount is $465,000.  This project is anticipated to be completed during the 2016 construction season.

 

11th Aldermanic District

 

Area bounded by W. Montana St., W. Oklahoma Ave., S. 44th St., and S. 49th St. (SM494150203) File Number 141727:  Sanitary sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $267,000).  The total estimated cost for this project including the requested amount is $282,000.  This project is anticipated to be completed during the 2015 construction season.

 

15th Aldermanic District

 

W. Galena St. - N. 26th St. to N. 30th St. (SM495150061) File Number 150997:  Combined sewer relay and lining.  (Nonassessable Sewer Maintenance Relay Fund -- $780,000).  The total estimated cost for this project including the requested amount is $800,000.  This project is anticipated to be completed during the 2016 construction season.

 

W. Walnut St. - N. 26th St. to N. 27th St. (SM495150062) File Number 150997:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $1,080,000).  The total estimated cost for this project including the requested amount is $1,100,000.  This project is anticipated to be completed during the 2016 construction season.

 

City Wide

 

2016 Sanitary Manhole Inspection Project (SM494150204) File Number 151137:  (Infiltration/Inflow Reduction Fund -- $120,000).  The total estimated cost for this project including the requested amount is $121,000.  This project is anticipated to be completed during the 2016 construction season.

 

2016 Sewer Structures Inspection Project (SM495150102) File Number 151137:  (Nonassessable Sewer Maintenance Relay Fund -- $36,500).  The total estimated cost for this project including the requested amount is $37,500.  This project is anticipated to be completed during the 2016 construction season.

 

Seal coating of various streets by contract (ST211150186) File Number 141515:  (Nonassessable Reconstruction Paving Fund -- $20,000, Additional Funds).  The total estimated cost for this project including the requested amount is $460,000.  This project is anticipated to be completed during the 2015 construction season.

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 