File #: 150997    Version:
Type: Resolution Status: Passed
File created: 11/2/2015 In control: COMMON COUNCIL
On agenda: Final action: 11/24/2015
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $563,000 for a total estimated cost of these projects being $11,172,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
12/2/20151 MAYOR SIGNED   Action details Meeting details Not available
11/24/20151 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Video Video
11/11/20151 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski - Department of Public Works
Pass4:0 Action details Meeting details Video Video
11/11/20151 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Proposed Substitute A
Pass4:0 Action details Meeting details Video Video
11/2/20150 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

150997

Version

Substitute 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $563,000 for a total estimated cost of these projects being $11,172,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $563,000 with the total cost estimated to be $11,172,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

2nd Aldermanic District

 

N. 76th St. - 290 feet south of W. Grantosa Dr. to W. Medford Ave. (SM495150084):  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $171,000.  This project is anticipated to be completed during the 2016 construction season.

 

4th Aldermanic District

 

N. Emmber Ln. at 400 feet south of W. Mt. Vernon Ave. (WT410150780):  Water repair work.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2015 construction season.

 

W. Juneau Ave. - N. 27th St. to N. 28th St. (SM495150060):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $265,000.  This project is anticipated to be completed during the 2016 construction season.

 

E. Michigan St. - N. Jackson St. to N. Van Buren St. (SM495150078):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $28,000.  This project is anticipated to be completed during the 2016 construction season.

 

E. Michigan St. - N. Milwaukee St. to N. Water St. (SM495150077):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $141,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. Prospect Ave. - E. Wells St. to E. Kilbourn Ave. (SM495150057):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $112,000.  This project is anticipated to be completed during the 2016 construction season.

 

W. State St. - N. 34th St. to N. 35th St. (SM495150081):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $35,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. Van Buren St. - E. Wisconsin Ave. to a point south of E. Michigan St. (SM495150079):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $90,000.  This project is anticipated to be completed during the 2016 construction season.

 

W. Vliet St. - N. 13th St. to N. 14th St. (SM495150055):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $85,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 4th St. - W. State St. to W. Juneau Ave. (WT410160781):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $22,000; Nonassessable Water Fund Budget Line 6410 -- $23,000).  The total estimated cost for this project including the requested amount is $750,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 12th St. - 200 feet north of W. Wells St. to W. Kilbourn Ave. (SM495150086):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $67,000.  This project is anticipated to be completed during the 2016 construction season.

 

N.15th St. - W. Highland Blvd. to W. Juneau Ave. (SM495150092):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $140,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 17th St. - W. Kilbourn Ave. to W. Highland Ave. (SM495150063):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $619,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 18th St. - 200 feet south of W. Highland Ave. to W. Highland Ave. (SM495150091):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $65,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 19th St. - W. McKinley Ave. to W. Vliet St. (SM495150073):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $507,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 21st St. - W. State St. to W. Highland Ave. (SM495150071):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $72,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 22nd St. - W. State St. to W. Highland Ave. (SM495150064):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $82,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 23rd St. - W. State St. to W. Highland Ave. (SM495150070):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $57,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 25th St. - W. McKinley Ave. to W. Juneau Ave. (SM495150087):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $112,000.  This project is anticipated to be completed during the 2016 construction season.

 

4th and 15th Aldermanic Districts

 

N. 27th St. and W. Vliet St., N. 27th St. and W. Cherry St. (Intersections) (SM495150059):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $109,000.  This project is anticipated to be completed during the 2016 construction season.

 

6th Aldermanic District

 

N. 6th St. - W. Vine St. to W. Brown St. (SM495150083):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $131,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 10th St. and easement north of N. 10th St. (Ext’d) - W. Galena St. (Ext’d) to south of W. Vine St. (Ext’d) (SM495150075):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $239,000.  This project is anticipated to be completed during the 2016 construction season.

 

8th Aldermanic District

 

W. Lincoln Ave. - S. 26th St. to S. Layton Blvd. (SM495150080):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $74,000.  This project is anticipated to be completed during the 2016 construction season.

 

S. 25th St. - W. Greenfield Ave. to W. Orchard St. (SM495150065):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $110,000.  This project is anticipated to be completed during the 2016 construction season.

 

8th and 12th Aldermanic Districts

 

W. Greenfield Ave. - S. 17th St. to S. 26th St. (SM495150066):  Combined sewer relay and lining.  (Nonassessable Sewer Maintenance Relay Fund -- $20,000).  The total estimated cost for this project including the requested amount is $1,166,000.  This project is anticipated to be completed during the 2016 construction season.

 

W. Lincoln Ave. - S. 20th St. to S. 21st St. (SM495150076):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $222,000.  This project is anticipated to be completed during the 2016 construction season.

 

10th Aldermanic District

 

N. 55th St. - W. Lloyd St. to W. Garfield Ave. (SM495150052):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $56,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 61st St. - W. St. Paul Ave. to 250 feet north of W. St. Paul Ave. (SM495150072):  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $53,000.  This project is anticipated to be completed during the 2016 construction season.

 

10th and 15th Aldermanic Districts

 

W. Lloyd St. - N. 48th St. to N. 53rd St. (SM495150056):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $20,000).  The total estimated cost for this project including the requested amount is $1,006,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 51st St. - W. Lloyd St. to W. Garfield Ave. (SM495150053):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $189,000.  This project is anticipated to be completed during the 2016 construction season.

 

12th Aldermanic District

 

W. Lincoln Ave. - S. 7th St. to S. 8th St. (SM495150082):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $66,000.  This project is anticipated to be completed during the 2016 construction season.

 

14th Aldermanic District

 

S. Kinnickinnic Ave. - 100 feet north of E. Malvern Pl. to E. Ohio Ave. (SM495150058):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $41,000.  This project is anticipated to be completed during the 2016 construction season.

 

15th Aldermanic District

 

W. Center St. - N. 25th St. to N. 26th St. (SM495150088):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $117,000.  This project is anticipated to be completed during the 2016 construction season.

 

W. Galena St. - N. 26th St. to N. 30th St. (SM495150061):  Combined sewer relay and lining.  (Nonassessable Sewer Maintenance Relay Fund -- $20,000).  The total estimated cost for this project including the requested amount is $778,000.  This project is anticipated to be completed during the 2016 construction season.

 

W. Lloyd St. (Ext’d) - South of W. Fond du Lac Ave. to N. 20th St. (SM495150051):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $273,000.  This project is anticipated to be completed during the 2016 construction season.

 

W. North Ave. - N. Teutonia Ave. to N. 14th St. (SM495150067):  Combined sewer lining and repair.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $225,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. Sherman Blvd. - W. Lisbon Ave. to W. North Ave. (SM495150054):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $104,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. Teutonia Ave. - W. North Ave. to a point 100 feet north of W. North Ave. (SM495150068):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2016 construction season.

 

W. Walnut St. - N. 26th St. to N. 27th St. (SM495150062):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $20,000).  The total estimated cost for this project including the requested amount is $1,029,000.  This project is anticipated to be completed during the 2016 construction season.

 

W. Wright St. - N. 11th St. to N. 15th St. (SM495150069):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $595,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 20th St. - W. North Ave. to W. Wright St. (SM495150074):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $20,000).  The total estimated cost for this project including the requested amount is $895,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 26th St. - W. Center St. to 300 feet north of W. Center St. (SM495150089):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $86,000.  This project is anticipated to be completed during the 2016 construction season.

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/Denise Reinholtz

Npr 4