powered help
header-left header-center header-right
File #: 150616    Version:
Type: Resolution Status: Passed
File created: 9/1/2015 In control: COMMON COUNCIL
On agenda: Final action: 9/22/2015
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $333,000 for a total estimated cost of these projects being $1,733,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number

150616

Version

Substitute 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $333,000 for a total estimated cost of these projects being $1,733,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $333,000 with the total cost estimated to be $1,733,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

1st Aldermanic District

 

Area bounded by W. Congress St., W. Hope Ave., N. 27th St., and the Soo Line Railroad (#2) (SM495150027):  Installing new storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $300,000, Additional Funds).  The total estimated cost for this project including the requested amount is $1,500,000.  This project is anticipated to be completed during the 2016 construction season.

 

5th Aldermanic District

 

Menomonee River Group - Bioswale Project:  N. Menomonee River Pkwy. - N. Swan Blvd. to W. Burleigh St. (Portions in the City of Wauwatosa) (SM499150108):  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $1,000).  The total estimated cost for this project including the requested amount is $30,000.  This project is anticipated to be completed during the 2015 construction season.

 

15th Aldermanic District

 

W. Lloyd St. - N. 60th St. to W. Lisbon Ave. (WT410160007):  Hydrant alteration.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $30,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 41st St. - W. Lloyd St. to W. Garfield Ave.; and, N. 45th St. - W. Garfield Ave. to W. North Ave. (ST214150103):  Install traffic calming devices.  (Nonassessable Reconstruction Paving Fund -- $1,000).  The total estimated cost for this project including the requested amount is $15,000.  This project is anticipated to be completed during the 2015 construction season.

 

N. 42nd St. - W. Lloyd St. to W. Garfield Ave. (ST211150189):  Install traffic calming devices.  (Nonassessable Reconstruction Paving Fund -- $1,000).  The total estimated cost for this project including the requested amount is $8,000.  This project is anticipated to be completed during the 2015 construction season.

 

City of Wauwatosa

 

N. Menomonee River Pkwy. - W. Concordia Ave. to 550 feet north of W. Concordia Ave. (WT410160717):  Water main relay and rehabilitation.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2016 construction season.

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/Denise Reinholtz

Npr 1

09/03/2015