File #: 150323    Version:
Type: Resolution Status: Passed
File created: 6/23/2015 In control: COMMON COUNCIL
On agenda: Final action: 7/21/2015
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $13,314,000 for a total estimated cost of these projects being $14,047,000.
Sponsors: THE CHAIR

Number

150323

Version

Substitute 1

Reference

140039

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $13,314,000 for a total estimated cost of these projects being $14,047,000.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $13,314,000.  The total estimated cost of these projects is $14,047,000.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

1st, 2nd and 7th Aldermanic Districts

 

Area bounded by W. Villard Ave., W. Hampton Ave., N. Sherman Blvd., and W. Fond du Lac Ave. (SM494140205) File Number 140039:  Sanitary Sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $3,775,000).  The total estimated cost for this project including the requested amount is $3,800,000.  This project is anticipated to be completed during the 2015 construction season.

 

2nd and 5th Aldermanic Districts

 

Area bounded by W. Villard Ave., W. Hampton Ave., W. Fond du Lac Ave., and N. 91st St. (SM494140208) File Number 140280:  Sanitary Sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $2,759,000).  The total estimated cost for this project including the requested amount is $2,784,000.  This project is anticipated to be completed during the 2015 construction season.

 

3rd Aldermanic District

 

Terrace Ave. Bioswales:  N. Terrace Ave. - E. Belleview Pl. to E. Lafayette Pl. (SM499150106) File Number 150322:  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $295,000).  The total estimated cost for this project including the requested amount is $300,000.  This project is anticipated to be completed during the 2015 construction season.

 

6th Aldermanic District

 

Area bounded by W. Capitol Dr., W. Finn Pl., N. 8th St., and N. 24th St. (SM494140202) File Number 140039:  Sanitary Sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $1,688,000).  The total estimated cost for this project including the requested amount is $1,713,000.  This project is anticipated to be completed during the 2015 construction season.

 

7th Aldermanic District

 

Area bounded by W. Congress St., W. Capitol Dr., N. 35th St., and N. 50th St. (SM494140203) File Number 140039:  Sanitary Sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $1,657,000).  The total estimated cost for this project including the requested amount is $1,682,000.  This project is anticipated to be completed during the 2015 construction season.

 

N. 54th Blvd. - W. Vienna Ave. to 115 feet north of W. Melvina St. (SM495150049) File Number 150322:  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $330,000).  The total estimated cost for this project including the requested amount is $350,000.  This project is anticipated to be completed during the 2015 construction season.

 

7th and 15th Aldermanic Districts

 

Sherman Blvd. Bioswales:  N. Sherman Blvd. - W. Lisbon Ave. to W. Burleigh St. (SM499150107) File Number 150322:  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $395,000).  The total estimated cost for this project including the requested amount is $400,000.  This project is anticipated to be completed during the 2015 construction season.

 

8th Aldermanic District

 

W. Lincoln Ave. - S. 35th St. to S. 37th St. (SM495140026) File Number 131475:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $335,000).  The total estimated cost for this project including the requested amount is $350,000.  This project is anticipated to be completed during the 2015 construction season.

 

W. Mitchell St. - S. 37th St. to Miller Park Way (SM495140068) File Number 140705:  Storm and sanitary sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $135,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2015 construction season.

 

W. Scott St. - S. 36th St. to S. 38th St. (SM495140022) File Number 131475:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $310,000).  The total estimated cost for this project including the requested amount is $325,000.  This project is anticipated to be completed during the 2015 construction season.

 

S. 34th St. - W. Rogers St. to W. Becher St. (SM495130066) File Number 130599:  Storm sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $115,000).  The total estimated cost for this project including the requested amount is $127,000.  This project is anticipated to be completed during the 2015 construction season.

 

S. 36th St. - W. Greenfield Ave. to W. Scott St. (SM495140074) File Number 140818:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $168,000).  The total estimated cost for this project including the requested amount is $183,000.  This project is anticipated to be completed during the 2015 construction season.

 

S. 37th St. - W. Lincoln Ave. to W. Grant St. (SM495140025) File Number 131475:  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $50,000).  The total estimated cost for this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2015 construction season.

 

10th Aldermanic District

 

W. Wells St. - N. 51st St. to N. 55th St. (SM495150011) File Number 141597:  Sanitary sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $144,000).  The total estimated cost for this project including the requested amount is $159,000.  This project is anticipated to be completed during the 2015 construction season.

 

N. 48th St. - W. Vliet St. to W. Cherry St. (SM495150019) File Number 141727:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $135,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2015 construction season.

 

10th and 15th Aldermanic Districts

 

W. Vliet St. - N. 45th St. to N. 49th St. (SM495150004) File Number 141514:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $283,000).  The total estimated cost for this project including the requested amount is $296,000.  This project is anticipated to be completed during the 2015 construction season.

 

12th Aldermanic District

 

W. Florida St. - S. 1st St. to a point east of S. 6th St. (TD07584011) File Number 150322:  Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (5-foot width of tree border area), and grading.  (TID 75 Nonassessable Paving Fund -- $220,000).  The total estimated cost for this project is $250,000.  This project is anticipated to be completed during the 2015 construction season.

 

W. Lincoln Ave. - S. 14th St. to S. 15th St. (SM495140061) File Number 140432:  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $115,000).  The total estimated cost for this project including the requested amount is $130,000.  This project is anticipated to be completed during the 2015 construction season.

 

S. 4th St. - 85 feet m/l north of W. Florida St. to W. Virginia St. (SM495140044) File Number 141837:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $190,000, Additional Funds).  The total estimated cost for this project including the requested amount is $425,000.  This project is anticipated to be completed during the 2015 construction season.

 

14th Aldermanic District

 

W. Lincoln Ave. - S. Chase Ave. to 400 feet m/l west of S. Chase Ave. (SM495140077) File Number 140818:  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $161,000).  The total estimated cost for this project including the requested amount is $173,000.  This project is anticipated to be completed during the 2015 construction season.

 

15th Aldermanic District

 

W. Kneeland St. at a point west of N. 18th Ct. (ST211150210) File Number 150322:  Replace traffic calming speed hump.  (Nonassessable Reconstruction Paving Fund -- $4,000).  The total estimated cost for this project is $5,000.  This project is anticipated to be completed during the 2015 construction season.

 

Various Aldermanic Districts

 

Crackfilling of various streets (ST211140164) File Number 131242:  (Nonassessable Reconstruction Paving Fund -- $50,000, Additional Funds).  The total estimated cost for his project including the requested amount is $235,000.  This project is anticipated to be completed during the 2015 construction season.

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/Denise Reinholtz

Nfr 14

07/02/2015

 

Technical correction made to contract number in the 3rd aldermanic district - LME  7/9/15