powered help
header-left header-center header-right
File #: 150118    Version:
Type: Resolution Status: Passed
File created: 5/12/2015 In control: COMMON COUNCIL
On agenda: Final action: 6/2/2015
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,482,000 for a total estimated cost of these projects being $14,332,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
150118
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,482,000 for a total estimated cost of these projects being $14,332,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $1,482,000 with the total cost estimated to be $14,332,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:
 
1st Aldermanic District
 
W. Atkinson Ave. - 140 feet northwest of N. Teutonia Ave. to W. Roosevelt Dr. (WT410160690):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $10,000; Nonassessable Water Fund Budget Line 6410 -- $10,000).  The total estimated cost for this project including the requested amount is $225,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Boehlke Ave. - N. 42nd St. to N. 43rd St. (WT410160670):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $80,000 This project is anticipated to be completed during the 2016 construction season.
 
W. Good Hope Rd. (south side) - N. Teutonia Ave. to N. 38th St. (WT410160669):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Newton Pl. - N. 42nd St. to N. 43rd St. (WT410160701):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $105,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Olive St. - N. 22nd St. to W. Roosevelt Dr. (WT410160691):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $10,000; Nonassessable Water Fund Budget Line 6410 -- $10,000).  The total estimated cost for this project including the requested amount is $200,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Stark St. - N. 36th St. to N. 37th St. (WT410160665):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $85,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 22nd St. - W. Stark St. to W. Fairmount Ave. (WT410160684):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 23rd St. - W. Fairmount Ave. to W. Lincoln Creek Pkwy. (WT410160683):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $10,000; Nonassessable Water Fund Budget Line 6410 -- $10,000).  The total estimated cost for this project including the requested amount is $280,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 35th St. - W. Oriole Dr. to W. Florist Ave. (WT410160702):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $10,000; Nonassessable Water Fund Budget Line 6410 -- $10,000).  The total estimated cost for this project including the requested amount is $250,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 37th St. - W. Hampton Ave. to W. Fairmount Ave. (WT410160666):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $12,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $325,000.  This project is anticipated to be completed during the 2016 construction season.
 
2nd Aldermanic District
 
W. Bobolink Ave. - N. 64th St. to N. 65th St. (WT410160644):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $90,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Fairmount Ave. - N. 62nd St. to N. 63rd St. (WT410160675):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $85,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Gertrude Dr. - W. Stark St. to W. Palmetto Ave. (WT410160704):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $190,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Hope Ave. - N. 74th St. to N. 75th St. (WT410160656):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $90,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. Prentiss St. - W. Tallmadge Pl. to W. Sheridan Ave. (WT410160647):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $190,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Sheridan Ave. - N. 69th St. to N. 76th St. (WT410160646):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $20,000; Nonassessable Water Fund Budget Line 6410 -- $20,000).  The total estimated cost for this project including the requested amount is $610,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Stark St. - N. 67th St. to N. 68th St. (WT410160676):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $85,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Tallmadge Pl. - 350 feet south of N. Prentiss St. to N. Prentiss St. (WT410160645):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $90,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Thurston Ave. - N. 71st St. to N. 72nd St. (WT410160638):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $125,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 65th St. - W. Carmen Ave. to W. Florist Ave. (WT410160642):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $12,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $325,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 67th St. - W. Bobolink Ave. to W. Florist Ave. (WT410160641):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $155,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 67th St. - W. Stark St. to W. Villard Ave. (WT410160673):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $15,000; Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project including the requested amount is $455,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 68th St. - W. Fond du Lac Ave. to W. Stark St. (WT410160672):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $175,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 69th St. - W. Fiebrantz Ave. to W. Marion St. (WT410160657):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $12,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $320,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 71st St. - W. Thurston Ave. to W. Bobolink Ave. (WT410160639):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $10,000; Nonassessable Water Fund Budget Line 6410 -- $10,000).  The total estimated cost for this project including the requested amount is $250,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 74th St. - W. Custer Ave. to W. Tallmadge Pl. (WT410160648):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $180,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 78th St. - W. Luscher Ave. to W. Gertrude Dr. (WT410160703):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $175,000.  This project is anticipated to be completed during the 2016 construction season.
 
3rd Aldermanic District
 
E. Belleview Pl. - N. Downer Ave. to N. Lake Dr. (WT410160688):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $190,000.  This project is anticipated to be completed during the 2016 construction season.
 
E. Belleview Pl. - N. Wahl Ave. to N. Terrace Ave. (WT410160687):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $70,000.  This project is anticipated to be completed during the 2016 construction season.
 
E. Kane Pl. - N. Prospect Ave. to N. Summit Ave. (WT410160664):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. Summit Ave. - E. Belleview Pl. to N. Downer Ave. (WT410160689):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. Summit Ave. - E. Kane Pl. to E. Lafayette Pl. (WT410160663):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $185,000.  This project is anticipated to be completed during the 2016 construction season.
 
4th Aldermanic District
 
N. 17th St. - W. Wisconsin Ave. to W. Wells St. (WT410160652):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $135,000.  This project is anticipated to be completed during the 2016 construction season.
 
5th Aldermanic District
 
W. Congress St. - N. 99th St. to N. 100th St. (WT410160630):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $95,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Green Tree Rd. - N. Park Manor Dr. to N. 99th St. (WT410160653):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $185,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Vera Ave. - N. Park Manor Dr. to N. 97th St. (WT410160654):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $195,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 92nd St. (Both Sides) - W. Center St. to W. Locust St. (WT410160659):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $12,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $325,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 95th St. - 170 feet north of W. Concordia Ave. to W. Townsend St. (WT410160694):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $125,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 95th St. - W. Sarasota Pl. to W. Fiebrantz Ave. (WT410160651):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $95,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 98th St. - W. Capitol Dr. to 85 feet north of W. Sarasota Pl. (WT410160650):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $105,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 98th St. - W. Center St. to W. Tower View Blvd. (WT410160660):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $12,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $325,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 99th St. - W. Vienna Ave. to W. Metcalf Pl. (WT410160667):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2016 construction season.
 
6th Aldermanic District
 
E. Center St. - N. 1st St. to N. Hubbard St. (WT410160706):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $160,000.  This project is anticipated to be completed during the 2016 construction season.
 
E. Locust St. - N. Palmer St. to N. 1st St. (WT410160705):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $95,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Locust St. - N. Dr. Martin Luther King Jr. Dr. to N. 4th St. (WT410160708):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $80,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. Palmer St. - E. Hadley St. to E. Locust St. (WT410160707):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2016 construction season.
 
7th Aldermanic District
 
W. Congress St. - N. 40th St. to N. 41st St. (WT410160682):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $80,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Locust St. - N. 29th St. to W. Fond du Lac Ave. (WT410160679):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $190,000.  This project is anticipated to be completed during the 2016 construction season.
 
8th Aldermanic District
S. 35th St. - W. Greenfield Ave. to W. Mitchell St. (WT410160004):  Hydrant alteration.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $45,000.  This project is anticipated to be completed during the 2016 construction season.
 
9th Aldermanic District
 
W. Woolworth Ave. - N. 46th St. to 690 feet west of N. 46th St. (WT410160001):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $175,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 62nd St. - W. Carmen Ave. to W. Bobolink Ave. (WT410160643):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $155,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 63rd St. - W. Bobolink Ave. to W. Florist Ave. (WT410160640):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $160,000.  This project is anticipated to be completed during the 2016 construction season.
 
10th Aldermanic District
 
S. Hawley Rd. - W. Main St. to Rail Road Right-of-Way (SM495140073):  Relaying sanitary sewer and storm sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $40,000, Additional Funds).  The total estimated cost for this project including the requested amount is $480,000.  This project is anticipated to be completed during the 2015 construction season.
 
11th Aldermanic District
 
W. Arizona St. - S. 53rd St. to east of S. 55th St. (WT410160699):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Euclid Ave. - S. 53rd St. to S. 55th St. (WT410160696):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2016 construction season.
 
Lynndale Neighborhood - Joint City of Greenfield Project (SM495150028):  Installing new storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $75,000, Additional Funds).  The total estimated cost for this project including the requested amount is $275,000.  This project is anticipated to be completed during the 2015 construction season.
 
W. Stack Dr. - S. 51st St. to S. 56th St. (WT410160692):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $15,000; Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project including the requested amount is $480,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Stack Dr. - S. 58th St. to S. 60th St. (WT410160693):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $80,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Tripoli Ave. - S. 67th St. to S. 68th St. (WT410160668):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $105,000.  This project is anticipated to be completed during the 2016 construction season.
 
S. 53rd St. - 15 feet south of W. Montana St. to W. Dakota St. (WT410160697):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2016 construction season.
 
S. 53rd St. - W. Oklahoma Ave. to W. Stack Dr. (WT410160698):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $130,000.  This project is anticipated to be completed during the 2016 construction season.
 
S. 54th St. - W. Oklahoma Ave. to W. Ohio Ave. (WT410160695):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $12,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $320,000.  This project is anticipated to be completed during the 2016 construction season.
 
12th Aldermanic District
 
W. Burnham St. - S. 10th St. to S. 11th St. (WT410160662):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $95,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Pierce St. - S. 9th St. to S. 10th St. (WT410160649):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $90,000.  This project is anticipated to be completed during the 2016 construction season.
 
S. 3rd St. - 205 feet north of W. Walker St. to W. Walker St. (WT410160685):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $55,000.  This project is anticipated to be completed during the 2016 construction season.
 
S. 10th St. - W. Burnham St. to W. Rogers St. (north line) (WT410160661):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2016 construction season.
 
S. 12th St. - W. Harrison Ave. to W. Cleveland Ave. (WT410160700):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $195,000.  This project is anticipated to be completed during the 2016 construction season.
 
S. 13th St. - W. Forest Home Ave. to W. Windlake Ave. (WT410160003):  Hydrant alteration.  (Nonassessable Water Fund Budget Line 5010 - 7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2016 construction season.
 
13th Aldermanic District
 
W. Henry St. - S. 23rd St. to 100 feet m/l west of S. 23rd St. (SM495150044):  Storm sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $40,000.  This project is anticipated to be completed during the 2016 construction season.
 
S. 1st St. - W. Norwich St. to 340 feet south of W. Norwich St. (WT410160678):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $85,000.  This project is anticipated to be completed during the 2016 construction season.
 
14th Aldermanic District
 
S. Chase Ave. - W. Lincoln Ave. to 200 feet m/l south of W. Lincoln Ave. (SM495150043):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $222,000.  This project is anticipated to be completed during the 2015 construction season.
 
S. Clement Ave. at E. Wilbur Ave. (ST211150199):  Intersection modification.  (Nonassessable Reconstruction Paving Fund -- $5,000, Additional Funds).  The total estimated cost for this project including the requested amount is $30,000.  This project is anticipated to be completed during the 2015 construction season.
 
S. 9th St. - W. Montana St. to W. Dakota St. (WT410160635):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $160,000.  This project is anticipated to be completed during the 2016 construction season.
 
S. 11th St. - W. Cleveland Ave. to 435 feet south of W. Cleveland Ave. (WT410160636):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $110,000.  This project is anticipated to be completed during the 2016 construction season.
 
S. 12th St. - 25 feet south of W. Cleveland Ave. to 410 feet south of W. Cleveland Ave. (WT410160637):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2016 construction season.
 
15th Aldermanic District
 
W. Galena St. - N. 35th St. to N. 40th St. (WT410160709):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $15,000; Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project including the requested amount is $400,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 16th St. - W. Hadley St. to W. Locust St. (WT410160634):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 22nd St. at W. Galena St. (ST211150201):  Removing traffic circle and paving with concrete.  (Nonassessable Reconstruction Paving Fund -- $10,000).  The total estimated cost for this project including the requested amount is $40,000.  This project is anticipated to be completed during the 2015 construction season.
 
N. 32nd St. - W. Center St. to W. Locust St. (WT410160681):  Abandon water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 33rd St. - W. Hadley St. to W. Locust St. (WT410160680):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $170,000.  This project is anticipated to be completed during the 2016 construction season.
 
City of St. Francis
 
E. Cora Ave. - S. Rutland Ave. to S. Arctic Ave. (WT410160631):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $70,000.  This project is anticipated to be completed during the 2016 construction season.
 
S. Iowa Ave. - E. Norwich St. to E. Tesch Ave. (WT410160677):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $85,000.  This project is anticipated to be completed during the 2016 construction season.
 
S. Kansas Ave. (East Side) - E. Cora Ave. (north line) to E. Elizabeth Ave. (WT410160633):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $175,000.  This project is anticipated to be completed during the 2016 construction season.
 
E. Tripoli Ave. - S. Rutland Ave. to S. Arctic Ave. (WT410160632):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $85,000.  This project is anticipated to be completed during the 2016 construction season.
 
;and, be it
 
Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it
 
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
 
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
 
Requestor
Infrastructure Services Division
Drafter
Mary Dziewiontkoski/Denise Reinholtz
Npr 12
05/15/2015