File #: 141836    Version:
Type: Resolution Status: Passed
File created: 3/31/2015 In control: COMMON COUNCIL
On agenda: Final action: 4/21/2015
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $107,000 for a total estimated cost of these projects being $1,695,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
141836
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $107,000 for a total estimated cost of these projects being $1,695,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $107,000 with the total cost estimated to be $1,695,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

1st Aldermanic District

Area bounded by W. Congress St., W. Hope Ave., N. 27th St., and the Soo Line Railroad (#2) (SM495150027): Installing new storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $100,000). The total estimated cost for this project including the requested amount is $1,500,000. This project is anticipated to be completed during the 2015 construction season.

4th Aldermanic District

E. Clybourn St. - N. Van Buren St. to 285 feet m/l east of N. Van Buren St. (SM495150039): Combined large diameter sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $1,000). The total estimated cost for this project including the requested amount is $125,000. This project is anticipated to be completed during the 2015 construction season.

N. Van Buren St. - E. Clybourn St. to 225 feet m/l south of E. Clybourn St. (SM495150038): Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $1,000). The total estimated cost for this project including the requested amount is $40,000. This project is anticipated to be completed during the ...