File #: 141399    Version:
Type: Resolution Status: Passed
File created: 12/16/2014 In control: COMMON COUNCIL
On agenda: Final action: 1/21/2015
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,516,000 for a total estimated cost of these projects being $5,249,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
1/28/20151 MAYOR SIGNED   Action details Meeting details Not available
1/21/20151 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
1/7/20150 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Individual present: Mary Dziewiontkoski - Department of Public Works
Pass5:0 Action details Meeting details Video Video
1/7/20151 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass5:0 Action details Meeting details Video Video
12/16/20140 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
141399
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,516,000 for a total estimated cost of these projects being $5,249,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $1,516,000 with the total cost estimated to be $5,249,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:
 
3rd Aldermanic District
 
N. Downer Ave. - E. Newberry Blvd. to E. Locust St. (SM495140109):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $51,000.  This project is anticipated to be completed during the 2016 construction season.
 
6th Aldermanic District
 
W. Keefe Ave. - N. 17th St. to N. 22nd St. (SM495140107):  Relaying combined sewer and combined large diameter sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $25,000).  The total estimated cost for this project including the requested amount is $1,653,000.  This project is anticipated to be completed during the 2015 construction season.
 
N. 7th St. - W. Ring St. to W. Concordia Ave. (SM495140098):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $145,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 10th St. (Vacated) - W. Somers St. (Ext'd) to 100 feet m/l north of W. Galena Pl. (SM495140096):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $78,000.  This project is anticipated to be completed during the 2015 construction season.
 
7th Aldermanic District
 
N. 35th St. - W. Glendale Ave. to W. Courtland Ave. (SM495140097):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $125,000.  This project is anticipated to be completed during the 2016 construction season.
 
8th Aldermanic District
 
S. 32nd St. - W. Orchard St. to W. Greenfield Ave. (SM495140102):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $84,000.  This project is anticipated to be completed during the 2016 construction season.
 
10th Aldermanic District
 
W. Blue Mound Rd. - N. 72nd St. to 300 feet m/l west of N. 72nd St. (SM495140099):  Sanitary Sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $22,000.  This project is anticipated to be completed during the 2016 construction season.
 
W. Stevenson St. (Ext'd) - N. 65th St. to 250 feet m/l east of N. 65th St. (SM495140104):  Sanitary Sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $19,000.  This project is anticipated to be completed during the 2016 construction season.
 
S. 61st St. - 300 feet m/l south of W. Fairview Ave. to W. Fairview Ave. (SM495140100):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $43,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 71st St. - W. Stevenson St. to W. Mt Vernon Ave. (SM495140101):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $132,000.  This project is anticipated to be completed during the 2016 construction season.
 
N. 72nd St. - 100 feet m/l south of W. Dixon St. to W. Stevenson St. (SM495140103):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2016 construction season.
 
S. 73rd St. - W. Stevenson St. to W. Main St. (SM495140105):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $388,000.  This project is anticipated to be completed during the 2016 construction season.
 
12th Aldermanic District
 
W. Becher St. - S. 16th St. to S. 20th St. (SM495140106):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $25,000).  The total estimated cost for this project including the requested amount is $1,000,000.  This project is anticipated to be completed during the 2015 construction season.
 
13th Aldermanic District
 
S. 24th St. - W. Howard Ave. to W. Tripoli Ave. (SM495140108):  Storm sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $44,000.  This project is anticipated to be completed during the 2016 construction season.
 
City Wide
 
State Paving Projects Drains and Structures (SM495140110):  (Nonassessable Sewer Maintenance Relay Fund -- $500,000).  The total estimated cost for this project is $500,000.  This project is anticipated to be completed during the 2015 construction season.
 
2015 Indirect Account (SM495150001):  (Nonassessable Sewer Maintenance Relay Fund -- $800,000).  The total estimated cost for this project is $800,000.  This project is anticipated to be completed during the 2015 construction season.
 
;and, be it
 
Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it
 
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
 
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
 
Requestor
Infrastructure Services Division
Drafter
Mary Dziewiontkoski/Denise Reinholtz
Npr 6
12/30/2014