powered help
header-left header-center header-right
File #: 141397    Version:
Type: Resolution Status: Passed
File created: 12/16/2014 In control: COMMON COUNCIL
On agenda: Final action: 1/21/2015
Effective date:    
Title: Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $178,000 for a total estimated cost of these projects being $1,655,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Number
141397
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $178,000 for a total estimated cost of these projects being $1,655,000.
Analysis
This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed.  After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable.  A resolution will be submitted after the Public Hearing authorizing construction.  The City cost for engineering these projects is estimated to be $178,000 with the total cost estimated to be $1,655,000.
Body
Resolved, By the Common Council of the City of Milwaukee that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:
 
3rd and 6th Aldermanic Districts
 
N. Pierce St. - E. Center St. to E. Burleigh St. (ST211120159):  Paving the roadway with concrete.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $5,000, Additional Funds).  The total estimated cost for this project including the requested amount is $850,000.  This project is anticipated to be completed during the 2016 construction season.
 
4th Aldermanic District
 
Alley between W. Juneau Ave., W. McKinley Ave., N. 31st St., and N. 32nd St. (ST212140114):  Paving the alley with concrete.  Doing all the necessary grading pertaining to said work.  (Nonassessable Alley Paving Fund -- $5,000, Additional Funds).  The total estimated cost for this project including the requested amount is $95,000.  This project is anticipated to be completed during the 2015 construction season.
 
10th Aldermanic District
 
Alley between W. Main St., N. 61st St., N. 62nd St., and Lands North (ST212160110):  Paving the alley with concrete.  Doing all the necessary grading pertaining to said work.  (Nonassessable Alley Paving Fund -- $10,000).  The total estimated cost for this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2016 construction season.
 
11th Aldermanic District
 
W. Forest Home Ave. - S. 42nd St. to S. 45th St. (Including S. 43rd St. to a point south of W. Euclid Ave. and W. Oklahoma Ave. triangle) (ST211140144):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $8,000, Additional Funds).  The total estimated cost for this project including the requested amount is $500,000.  This project is anticipated to be completed during the 2015 construction season.
 
City Wide
 
2015 Administration Cost of Sidewalk Program (ST230150001):  (Nonassessable 2015 Budgeted Funds -- $150,000).  The total estimated cost for this project amount is $150,000.  This project is anticipated to be completed during the 2015 construction season.
 
; and, be it
 
Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it
 
Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it
 
Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works; and, be it
 
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
 
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
 
Requestor
Infrastructure Services Division
Drafter
Mary Dziewiontkoski/Denise Reinholtz
Apr 6
12/30/2014