File #: 080388    Version:
Type: Resolution Status: Passed
File created: 7/1/2008 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 7/30/2008
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,152,000 for a total estimated cost of these projects being $7,305,400.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter, 2. Hearing notice list, 3. Fiscal note, 4. Comptroller Certification for N. Teutonia Ave...

Number

080388

Version

SUBSTITUTE 1

Reference

080124

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,152,000 for a total estimated cost of these projects being $7,305,400.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $3,152,000.  The total estimated cost of these projects is $7,305,400.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

1st Aldermanic District

 

N. Teutonia Ave. over W. Silver Spring Dr. (Bridge and Approaches ST32002310/BR32000310) (2080-07-70) File Number 080124: Concrete deck and approach replacement. (Grantor Reimbursable Paving Fund -- $30,000 Additional Funds; Grantor Reimbursable Structure Fund -- $25,000 Additional Funds; City Share Non-Assessable Structure Fund -- $50,000 Additional Funds).

 

These funds are to be transferred to the construction account (ST32000310)

(2080-07-70).

 

Previously authorized for road construction:  $1,050,000.00.

 

Current estimated cost of the total project including this resolution:  $1,446,400.00.

 

Original estimated cost of the total project:  $439,000.00.

 

This project is anticipated to be completed during the 2008 construction season.

 

3rd Aldermanic District

 

E. Boylston St. - N. Warren Ave. to N. Cambride Ave. (SM495070098) File Number 080387: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $53,000).  The total estimated cost for this project including the requested amount is $53,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. Murray Ave. - E. Newberry Blvd. to E. Locust St. (SM495080055) File Number 080387: Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $100,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2008 construction season.

 

E. Newberry Blvd. - 350 feet m/l West of N. Oakland Ave. to N. Farwell Ave. (SM495070083) File Number 080124: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $486,000 Additional Funds).  The total estimated cost for this project including the requested amount is $776,000.  This project is anticipated to be completed during the 2008 construction season.

 

E. Riverside Pl. - N. Bartlett Ave. to N . Oakland Ave. (SM495070183) File Number 071167: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $65,000).  The total estimated cost for this project including the requested amount is $77,000.  This project is anticipated to be completed during the 2008 construction season.

 

4th Aldermanic District

 

N. 21st St. - A Point 100 feet north of W. Cherry St. to W. Galena St. (TD05888004) File Number 050276: Asphalt paving stage construction, construct sidewalk, construct curb and gutter, driveway approaches, sodding, grading and tree removal where necessary. (TID Nonassessable Paving Fund -- $99,000).  The total estimated cost for this project including the requested amount is $99,000.  This project is anticipated to be completed during the 2008 construction season.

 

4th and 15th Aldermanic Districts

 

W. Galena St. at N. 22nd St. (TD05888004) File Number 050276: Asphalt paving stage construction, construct sidewalk, construct curb and gutter, driveway approaches, sodding, grading and tree removal where necessary. (TID Nonassessable Paving Fund -- $143,000).  The total estimated cost for this project including the requested amount is $143,000.  This project is anticipated to be completed during the 2008 construction season.

 

7th and 10th Aldermanic Districts

 

N. 50th St. - 150 feet m/l North of W. Center St. to W. Locust St. (SM495070033) File Number 061380: Sanitary sewer lining and repair. (Nonassessable Sewer Maintenance Relay Fund -- $131,000).  The total estimated cost for this project including the requested amount is $141,000.  This project is anticipated to be completed during the 2008 construction season.

 

11th Aldermanic District

 

S. 55th St. (West Half) - W. Norwich St. to W. Howard Ave. (Sponsored by the City of Greenfield) (ST211080138) File Number 080387: Concrete pavement. (Nonassessable Reconstruction Paving Fund -- $15,000).  The total estimated cost for this project including the requested amount is $15,000.  This project is anticipated to be completed during the 2008 construction season.

 

15th Aldermanic District

 

N. 23rd St. - W. Brown St. to W. North Ave. (TD06584001) File Number 051275: Asphalt pavement reconstruction, replace all curb and gutter, sidewalk and driveway approaches, sodding, and grading.  (TID Nonassessable Paving Fund -- $295,000).  The total estimated cost for this project including the requested amount is $295,000.  This project is anticipated to be completed during the 2008 construction season.

 

City Wide

 

Sewer exams as requested. (SM495080009) File Number 080387: (Nonassessable Sewer Maintenance Relay Fund -- $60,000).  The total estimated cost for this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2008 construction season.

 

Storm water basin and drain replacement for 2008 paving projects. (SM495080049) File Number 080387: (Nonassessable Sewer Maintenance Relay Fund -- $200,000).  The total estimated cost for this project including the requested amount is $200,000.  This project is anticipated to be completed during the 2008 construction season.

 

City of Greenfield

 

W. Cold Spring Rd. - S. 51st St. to S. 60th St. (WT410071411) File Number 080124: Water main extension. (Nonassessable Water Fund -- $1,400,000 Additional Funds).  The total estimated cost for this project including the requested amount is $3,900,000.  This project is anticipated to be completed during the 2008 construction season.

 

; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

mld:dr

nfr 13