powered help
header-left header-center header-right
File #: 140705    Version:
Type: Resolution Status: Passed
File created: 9/3/2014 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 9/23/2014
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $198,000 for a total estimated cost of these projects being $3,187,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Hearing Notice List
Number
140705
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $198,000 for a total estimated cost of these projects being $3,187,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $198,000 with the total cost estimated to be $3,187,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

1st Aldermanic District

N. Teutonia Ave. - W. Capitol Dr. to W. Ruby Ave. (SM495140065): Sanitary lining and storm relay. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $1,458,000. This project is anticipated to be completed during the 2015 construction season.

N. Teutonia Ave. - W. Capitol Dr. to W. Ruby Ave. (WT410150001): Hydrant alteration. (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000). The total estimated cost for this project including the requested amount is $160,000. This project is anticipated to be completed during the 2015 construction season.

4th Aldermanic District

Highland Community School Bioswales - 1706 W. Highland Blvd. and on W. Juneau Ave. - N. 17th St. to N. 18th St. (SM493130110): (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $1,000). The total estimated cost for this project including the requested amount is $15,000. This project is anticipated to...