File #: 140279    Version:
Type: Resolution Status: Passed
File created: 6/3/2014 In control: COMMON COUNCIL
On agenda: Final action: 6/24/2014
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $2,143,300 for a total estimated cost of $2,361,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. Updated Official Notice, 2. Transmittal Letter, 3. Official Notice, 4. Notice Published on 7-11-14
Number
140279
Version
SUBSTITUTE 1
Reference
121331
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $2,143,300 for a total estimated cost of $2,361,000.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $2,143,300. The total estimated cost of these projects is $2,361,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

1st Aldermanic District

Alley between W. Hampton Ave., N. Hopkins St., W. Stark St., and N. 39th St. (ST212140128) File Number 121331: Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, and storm drainage facilities where necessary. (Assessable Alley Paving Fund -- $10,600; Nonassessable Alley Paving Fund -- $50,000). The total estimated cost for this project including the requested amount is $70,000. This project is anticipated to be completed during the 2014-2015 construction season.

2nd and 10th Aldermanic Districts

N. 67th St. - W. Vienna Ave. to W. Capitol Dr. (ST211140122) File Number 120251: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (9-foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $23,200; Nonassessable Reconstruction Pa...

Click here for full text