File #: 140275    Version: 0
Type: Resolution Status: Passed
File created: 6/3/2014 In control: COMMON COUNCIL
On agenda: Final action: 6/24/2014
Effective date:    
Title: Resolution relative to the cost participation and installation of traffic control signals in conjunction with the Federal State aid paving and bridge construction on IH 43 from West Howard Avenue to the Valley Bridge in various Aldermanic Districts at a total estimated cost of $399,459.56, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation.
Sponsors: THE CHAIR
Indexes: FEDERAL GRANTS, TRAFFIC CONTROL SIGNALS
Attachments: 1. Executed Agreement, 2. Agreement, 3. Signal Schedule.pdf, 4. Unit Cost Analysis, 5. Comptrollers Certification
Number
140275
Version
ORIGINAL
Reference

Sponsor
THE CHAIR
Title
Resolution relative to the cost participation and installation of traffic control signals in conjunction with the Federal State aid paving and bridge construction on IH 43 from West Howard Avenue to the Valley Bridge in various Aldermanic Districts at a total estimated cost of $399,459.56, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation.
Analysis
This resolution authorizes the Commissioner of Public Works and Comptroller to enter into a funding agreement with the Wisconsin Department of Transportation for installation of traffic control signals in conjunction with the Federal State aid paving and bridge construction on IH 43 from West Howard Avenue to the Valley Bridge in various Aldermanic Districts at a total estimated cost of $399,459.56, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation, and to install these improvements upon execution of the agreement. This resolution also authorizes the Comptroller to establish and transfer funds to the appropriate accounts for the project. The total estimated cost of the entire project is $500,000, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation.
Body
Whereas, The Surface Transportation Program provides cost participation for traffic control signal improvements in conjunction with the paving of highways located on the Federal State Aid Highway System; and

Whereas, The traffic signals on ramp terminals and adjacent to IH 43 on South 4th Street and South 5th Street from West Howard Avenue to the Valley Bridge are maintained by the City of Milwaukee and will be impacted by paving and bridge construction, and

Whereas, The total estimated cost of this project is $369,869.96 for the alteration and upgrade of traffic control signals at impacted intersections due to bridge and ramp construction; and

Whereas, Th...