File #: 140146    Version:
Type: Resolution Status: Passed
File created: 5/13/2014 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 6/3/2014
Effective date:    
Title: Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $185,000 for a total estimated cost of these projects being $1,905,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Hearing Notice List
Number
140146
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $185,000 for a total estimated cost of these projects being $1,905,000.
Analysis
This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed.  After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable.  A resolution will be submitted after the Public Hearing authorizing construction.  The City cost for engineering these projects is estimated to be $185,000 with the total cost estimated to be $1,905,000.
Body
Resolved, By the Common Council of the City of Milwaukee that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:
 
3rd Aldermanic District
 
E. Newberry Blvd. - N. Downer Ave. to N. Oakland Ave. (ST211150155):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $40,000).  The total estimated cost for this project including the requested amount is $785,000.  This project is anticipated to be completed during the 2015 construction season.
 
E. Newberry Blvd. - N. Lake Dr. to N. Downer Ave. (ST211150154):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $30,000).  The total estimated cost for this project including the requested amount is $415,000.  This project is anticipated to be completed during the 2015 construction season.
 
5th Aldermanic District
 
W. Fairmount Ave. - N. 107th St. to N. 108th St. (ST211150159):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $20,000).  The total estimated cost for this project including the requested amount is $70,000.  This project is anticipated to be completed during the 2015 construction season.
 
10th Aldermanic District
 
W. St. Paul Ave. - N. 92nd St. to N. 95th St. (ST211150163):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $20,000).  The total estimated cost for this project including the requested amount is $160,000.  This project is anticipated to be completed during the 2015 construction season.
 
11th Aldermanic District
 
S. 85th St. - W. Morgan Ave. to W. Holt Ave. (ST211150162):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $20,000).  The total estimated cost for this project including the requested amount is $110,000.  This project is anticipated to be completed during the 2015 construction season.
 
12th Aldermanic District
 
S. 2nd St. - W. Oregon St. to W. Florida St. (CP Rail underpass sidewalk area) (ST211150158):  Retaining wall and railing repair.  Laying concrete walk.  Doing all necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $15,000).  The total estimated cost for this project including the requested amount is $80,000.  This project is anticipated to be completed during the 2015 construction season.
 
13th Aldermanic District
 
S. 21st St. - W. Van Norman Ave. to W. Whitaker Ave. (ST211150160):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $20,000).  The total estimated cost for this project including the requested amount is $140,000.  This project is anticipated to be completed during the 2015 construction season.
 
14th Aldermanic District
 
S. California St. - E. Euclid Ave. to E. Oklahoma Ave. (ST211150161):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $20,000).  The total estimated cost for this project including the requested amount is $145,000.  This project is anticipated to be completed during the 2015 construction season.
 
; and, be it
 
Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it
 
Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it
 
Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works; and, be it
 
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
 
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
 
Requestor
Infrastructure Services Division
Drafter
Mary Dziewiontkoski/Denise Reinholtz
Apr 12
05/16/2014