File #: 131564    Version: 0
Type: Resolution Status: Passed
File created: 3/4/2014 In control: COMMON COUNCIL
On agenda: Final action: 4/2/2014
Effective date:    
Title: Resolution authorizing the proper City officials to execute a State Municipal Agreement with the Wisconsin Department of Transportation for the City of Milwaukee utility alterations in conjunction with the Zoo Interchange’s Core, Phase I contract, at a total estimated cost of $260,727,770, with an estimated grantor share of $260,345,890 and an estimated City share of $381,880.
Sponsors: THE CHAIR
Indexes: EXPRESSWAYS, INTERGOVERNMENTAL AGREEMENTS, PUBLIC UTILITIES, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Map, 2. Agreement, 3. Approved Agreement - Signed, 4. Comptrollers Certification, 5. Hearing Notice list
Number
131564
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution authorizing the proper City officials to execute a State Municipal Agreement with the Wisconsin Department of Transportation for the City of Milwaukee utility alterations in conjunction with the Zoo Interchange's Core, Phase I contract, at a total estimated cost of $260,727,770, with an estimated grantor share of $260,345,890 and an estimated City share of $381,880.
Analysis
This resolution authorizes the Commissioner of Public Works and the Comptroller to execute the State Municipal Agreement for construction alterations on Milwaukee Water Works, City Underground Conduit, City of Milwaukee-Sanitary Sewer, and City of Milwaukee-Cable facilities in conjunction with the Zoo Interchange's Core, Phase I contract.  Total estimated cost of $260,727,770, with an estimated grantor share of $260,345,890 and an estimated City share of $381,880.  
Body
Whereas, The Wisconsin Department of Transportation (WISDOT) has scheduled the rehabilitation of the Zoo Interchange in the City of Milwaukee; and
 
Whereas, The Wisconsin Department of Transportation has scheduled the Zoo Interchange's Core, Phase I contract to be constructed from the fall of 2014 through the fall of 2015; and
 
Whereas, The Core, Phase I contract will include reconstruction on the north (USH 45) and east (I-94) legs of the Zoo Interchange, abutting frontage roads of West Adler Street and West Chester Street, the North 92nd Street and North 84th Street bridges over I-94, the West Blue Mound Road bridge over USH 45, and various other miscellaneous construction from North 70th Street to North 121st Street in the City of Milwaukee; and  
 
Whereas, Alterations to Milwaukee Water Works, City Underground Conduit, City of Milwaukee-Sanitary Sewer, and City of Milwaukee-Cable facilities are necessitated by the Zoo Interchange's Core, Phase I contract; and
 
Whereas, Wisconsin Statue 84.295(4m) indicates that the Wisconsin Department of Transportation will pay 90% of the cost of alteration, rehabilitation, and relocation of Municipal utilities with the responsible jurisdiction liable for the remaining 10% of the cost; and
 
Whereas, In order for the City to be reimbursed for the 90% share of the utility alteration construction cost on the Zoo Interchange's Core, Phase I contract, the Wisconsin Department of Transportation requires a State Municipal Agreement, in accord with WISDOT relocation assistance policy; and
 
Whereas, The Wisconsin Department of Transportation has provided the City with the necessary State Municipal Agreement to facilitate reimbursement of the City utility alteration construction costs associated with the Zoo Interchange's Core, Phase I contract; now, therefore, be it
 
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works is hereby authorized to execute the State Municipal Agreement for construction alterations on Milwaukee Water Works, City Underground Conduit, City of Milwaukee-Sanitary Sewer, and City of Milwaukee-Cable facilities in conjunction with the Zoo Interchange's Core, Phase I contract, attached to this resolution by reference as though set forth in full; and, be it
 
Further Resolved, That the funding to cover the 10% City cost of the Zoo Interchange's Core, Phase I contract utility alterations for the Milwaukee Water Works, City Underground Conduit, City of Milwaukee-Sanitary Sewer, and City of Milwaukee-Cable estimated to be $254,980, $16,000, $110,000, and $900 respectively, are or will be placed in Department of Public Works Departmental Accounts; and, be it
 
Further Resolved, That the City Comptroller is hereby authorized to create within the Capital Improvement Fund, Grant and Aid projects, the necessary Project Grant Chartfield Values for engineering and construction for the projects (expenditure) and transfer to any of these accounts the amounts required under the grant agreement and City Accounting Policy but not to exceed a 10 percent increase of the total amounts reserved for the grantor's share and local share or $5,000, whichever is greater, as follows:
 
Milwaukee Water Works Account Number
Zoo Interchange - Core Phase I Contract
 
City Share Non-Assessable Fund Water Works Department
South 86th Street - West Adler Street to 300 feet south of West Adler Street
1060-33-80
WT410140504
Fund 0420
$3,740
 
City Share Non-Assessable Fund Water Works Department
South 87th Street - West Adler Street to 300 feet south of West Adler Street
1060-33-80
WT410140506
Fund 0420
$3,630
 
City Share Non-Assessable Fund Water Works Department
South 87th Place - West Adler Street to 300 feet south of West Adler Street
1060-33-80
WT410140508
Fund 0420
$3,630
City Share Non-Assessable Fund Water Works Department
West Adler Street - South 91st Street to South 95th Street
1060-33-80
WT410140510
Fund 0420
$32,780
 
City Share Non-Assessable Fund Water Works Department
West Chester Street - 1000 feet east of South 92nd Street to South 92nd Street
1060-33-80
WT410140512
Fund 0420
$19,580
 
City Share Non-Assessable Fund Water Works Department
West Chester Street - South 92nd Street to West Dixon Street
1060-33-80
WT410140514
Fund 0420
$12,980
 
City Share Non-Assessable Fund Water Works Department
South 87th Place Extended (Freeway Crossing) - West Chester Street Extended to West Adler Street
1060-33-80
WT410140516
Fund 0420
$3,630
 
City Share Non-Assessable Fund Water Works Department
South 91st Street Extended (Freeway Crossing) - West Chester Street to West Adler Street
1060-33-80
WT410140518
Fund 0420
$39,820
 
City Share Non-Assessable Fund Water Works Department
West O'Connor Street - South 72nd Street to South 84th Street
1060-33-80
WT410140520
Fund 0420
$6,930
 
City Share Non-Assessable Fund Water Works Department
North 95th Street - West Blue Mound Road to West Wisconsin Avenue
1060-33-80
WT410140522
Fund 0420
$1,100
 
City Share Non-Assessable Fund Water Works Department
USH 45 Crossing (800 feet south of West Blue Mound Road) - Water Easement 248A (East of USH 45) to Water Easement 248D (West of USH 45)
1060-33-80
WT410140524
Fund 0420
$49,500
 
City Share Non-Assessable Fund Water Works Department
West Adler Street - 250 feet east of South 86th Street to South 87th Place
1060-33-80
WT410140528
Fund 0420
$22,110
 
City Share Non-Assessable Fund Water Works Department
West Adler Street (Adler Pumping Station) - 250 feet east of South 86th Street to South 87th Place
1060-33-80
WT410140530
Fund 0420
$55,000
 
City Share Non-Assessable Fund Water Works Department
West Dixon Street - South 71st Street
1060-33-80
WT410140540
Fund 0420
$550
 
Grantor Non-Reimbursable Share
$2,294,820
 
Total Estimated Milwaukee Water Works:
$2,549,800
 
City Underground Conduit Account Number
Zoo Interchange - Core, Phase I Contract
1060-33-80
ST280130209
Fund 0333
$16,000
 
Grantor Non-Reimbursable Share
$135,000
 
Total Estimated City Underground Conduit:
$151,000
 
City of Milwaukee-Sanitary Sewer Account Number
Zoo Interchange - Core, Phase I Contract
1060-33-80
SM495140050
Fund 0491
$110,000
 
Grantor Non-Reimbursable Share
$990,000
 
Total Estimated City of Milwaukee-Sanitary Sewer:
$1,100,000
 
City of Milwaukee-Cable Account Number
Zoo Interchange - Core, Phase I Contract
1060-33-80
ST270140773
Fund 0333
$900
 
Grantor Non-Reimbursable Share
$8,100
 
Total Estimated City of Milwaukee-Cable:
$9,000
 
Previously Authorized for Construction of Utility Alterations for the Zoo Interchange's Core, Phase I Contract:  $0
Current estimated cost for total project - Zoo Interchange's Core, Phase I Contract, including this resolution:  $260,727,770
Original estimated cost for total project - Zoo Interchange's Core Phase I Contract, including this resolution:  $260,727,770
 
Requestor
Department of Public Works
Drafter
Infrastructure Services Division
CTC:cn
February 25, 2014