powered help
header-left header-center header-right
File #: 080125    Version:
Type: Resolution Status: Passed
File created: 5/20/2008 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 6/10/2008
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $50,000 for a total estimated cost of these projects being $1,145,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter, 2. Fiscal note, 3. Hearing notice list
Number
080125
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $50,000 for a total estimated cost of these projects being $1,145,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $50,000 with the total cost estimated to be $1,145,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

5th and 10th Aldermanic Districts

N. 76th St. - W. Locust St. to W. Lisbon Ave. (SM495080016): Relaying sanitary sewer.
(Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $423,000. This project is anticipated to be completed during the 2008 construction season.

8th Aldermanic District

Alley bounded by W. Canal St., W. Milwaukee Rd. and S. Selig Dr. (TD05384013): Install new storm sewer. The total estimated cost for this project is $70,000. This project is anticipated to be completed during the 2008 construction season.

11th Aldermanic District

W. Howard Ave. - S. 56th St. to 145 feet east of S. 58th St. (WT410081417): Relaying water main. (Nonassessable Water Fund -- $15,000). The total estimated cost for this project including the requested amount is $100,000. This project is anticipated to be completed during the 2008 construction season.

12th Aldermanic District

W. Burnham St. - S. 12th St. to S. 14th St. (SM495080015): Relaying combined sewer.
(Nonassessable Sewer Maintenance...

Click here for full text