File #: 131476    Version:
Type: Resolution Status: Passed
File created: 2/11/2014 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 3/4/2014
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $12,234,000 for a total estimated cost of these projects being $17,082,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Capital Grant Resolution Certificate, 2. Hearing Notice List
Number
131476
Version
Substitute 1
Reference
131076
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $12,234,000 for a total estimated cost of these projects being $17,082,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $12,234,000. The total estimated cost of these projects is $17,082,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

1st Aldermanic District

Area bounded by W. Villard Ave., W. Custer Ave., N. Sherman Blvd., and N. 51st St. (SM494130207) File Number 131076: Sanitary Sewer lining. (Infiltration/Inflow Reduction Fund -- $795,000). The total estimated cost for this project including the requested amount is $815,000. This project is anticipated to be completed during the 2014 construction season.

1st and 7th Aldermanic Districts

W. Capitol Dr. (North Side) - N. 29th St. to 150 feet m/l west of N. 31st St. (SM495130043) File Number 130234: Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $250,000). The total estimated cost for this project including the requested amount is $265,000. This project is anticipated to be completed during the 2014 construction season.

2nd, 5th and 9th Aldermanic Districts

City of Milwaukee Various Locations - 10 Local Intersections (ST320120501)
(2984-08-05) File Number 111478: Install Monotube Mast Arms, concrete bases, poles and electrical condui...

Click here for full text