powered help
header-left header-center header-right
File #: 131450    Version: 0
Type: Resolution Status: Passed
File created: 2/11/2014 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 3/4/2014
Effective date:    
Title: Resolution relative to the cost participation and installation of temporary and permanent traffic control signals in conjunction with the reconstruction of the West Wisconsin Avenue bridge over USH 45 under Federal and State Aid construction of the Zoo Interchange Project in the 10th Aldermanic District at a total estimated cost of $59,639.79, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation.
Sponsors: THE CHAIR
Indexes: BRIDGES, TRAFFIC CONTROL SIGNALS
Attachments: 1. Cost Analysis, 2. Agreement, 3. Comptrollers Certificate, 4. Hearing Notice List
Number
131450
Version
ORIGINAL
Reference
111184
Sponsor
THE CHAIR
Title
Resolution relative to the cost participation and installation of temporary and permanent traffic control signals in conjunction with the reconstruction of the West Wisconsin Avenue bridge over USH 45 under Federal and State Aid construction of the Zoo Interchange Project in the 10th Aldermanic District at a total estimated cost of $59,639.79, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation.
Analysis
This resolution authorizes the Commissioner of Public Works and Comptroller to enter into a funding agreement with the Wisconsin Department of Transportation for installation of temporary and permanent traffic control signals in conjunction with the reconstruction of the West Wisconsin Avenue bridge over USH 45 under Federal and State Aid construction of the Zoo Interchange Project in the 10th Aldermanic District at a total estimated cost of $59,639.79, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation, and to install these improvements upon execution of the agreement. This resolution also authorizes the Comptroller to establish and transfer funds to the appropriate accounts for the project. The total cost of all phases of the Zoo Interchange Project for temporary and permanent street lighting and traffic control devices is $1,540,000, with one hundred percent of the total cost funded by the Wisconsin Department of Transportation.
Body
Whereas, The Wisconsin Department of Transportation is undertaking the reconstruction of the Zoo Interchange at IH 94, IH 894, and USH 45; and

Whereas, Preliminary engineering work by City of Milwaukee street lighting, traffic signals, and traffic signs staff was authorized under Common Council File Number 111184; and

Whereas, The Zoo Interchange project provides cost participation for traffic control improvements in conjunction with construction that impac...