Type: Resolution Status: Passed
File created: 4/15/2008 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 5/20/2008
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,283,600 for a total estimated cost of $1,516,600.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter, 2. OFFICIAL NOTICE NUMBER 112, 3. Hearing notice list, 4. Official Notice Number 112 ACTIONS, 5. Fiscal Note, 6. Notice Published on 6-6-08
Number
080001
Version
SUBSTITUTE 1
Reference
051660
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,283,600 for a total estimated cost of $1,516,600.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $1,283,600. The total estimated cost of these projects is $1,516,600.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

1st Aldermanic District

Alley between W. Hampton Ave., W. Stark St., N. 20th St. and N. 21st St. (ST212060123) File Number 051660: Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, and storm drainage facilities where necessary. (Assessable Alley Paving Fund -- $69,300; Nonassessable Alley Paving Fund -- $50,000). The total estimated cost for this project including the requested amount is $132,300. This project is anticipated to be completed during the 2008 construction season.

2nd Aldermanic District

W. Thurston Cr. - N. 76th St. to N. 78th St. (ST211070137): File Number 061097:
Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding, and grading. (Assessable Reconstruction Paving Fund -- $12,600; Nonassessable Reconstruction Paving Fund -- $55,000). The total estimated cost for thi...

Click here for full text