powered help
header-left header-center header-right
File #: 071490    Version:
Type: Resolution Status: Passed
File created: 2/26/2008 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 3/18/2008
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $15,000 for a total estimated cost of these projects being $350,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter, 2. Fiscal Note, 3. Hearing notice list
Number
071490
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $15,000 for a total estimated cost of these projects being $350,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $15,000 with the total cost estimated to be $350,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

Greenfield

W. Edgerton Ave. at W. Loomis Rd. (WT410081107): Water main alteration. (Nonassessable Water Fund -- $15,000). The total estimated cost for this project including the requested amount is $150,000. This project is anticipated to be completed during the 2009 construction season.

Various Aldermanic Districts

Various Locations (ST211080129): Asphalt resurfacing of various streets by contract. The total estimated cost for this project is $200,000. This project is anticipated to be completed during the 2008 construction season.

; and, be it

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

Requestor
Infrastructure Services Di...

Click here for full text