Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $65,000 for a total estimated cost of these projects being $2,526,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter, 2. Fiscal note, 3. Hearing notice
Number
071264
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $65,000 for a total estimated cost of these projects being $2,526,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $65,000 with the total cost estimated to be $2,526,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

3rd Aldermanic District

E. Park Pl. - N. Prospect Ave. to N. Stowell Ave. (SM495070179): Combined sewer lining. The total estimated cost for this project is $61,000. This project is anticipated to be completed during the 2008 construction season.

6th Aldermanic District

N. Commerce St. - N. Humboldt Ave. to N. Weil St. (WT410080022): Water main extension. (Nonassessable Water Fund -- $15,000). The total estimated cost for this project including the requested amount is $225,000. This project is anticipated to be completed during the 2008 construction season.

8th Aldermanic District

W. Mitchell St. - S. 31st St. to S. 32nd St. (SM495070202): Relaying combined sewer. The total estimated cost for this project is $74,000. This project is anticipated to be completed during the 2008 construction season.

11th Aldermanic District

W. Oklahoma Ave. - S. 60th St. to 550’ west of W. Lakefield Dr. (WT410081106): Water main extension. (Nonassessable Water Fund -- $50,000). The total estimated cost for this project including the requested amount is $2,000,000. This pro...