powered help
header-left header-center header-right
File #: 070783    Version:
Type: Resolution Status: Passed
File created: 9/25/2007 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 10/23/2007
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,149,000 for a total estimated cost of these projects being $11,623,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter, 2. Fiscal note
Number
070783
Version
SUBSTITUTE 1
Reference
061096
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,149,000 for a total estimated cost of these projects being $11,623,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $3,149,000. The total estimated cost of these projects is $11,623,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

1st Aldermanic District

N. 27th St. at W. Villard Ave. (SW170060104) File Number 061096: Sanitary sewer relocation. (Nonassessable Expansion of Capacity Sewer Fund -- $35,000, additional funds.) File Number 061096 authorized $251,000. The total estimated cost for this project including the requested amount is $286,000. This project is anticipated to be completed during the 2007 construction season.

4th Aldermanic District

Local Street Project - Marquette Interchange Cleanup (ST320021203) (1060-05-07) File Number 070524: Adjustments to City of Milwaukee water and underground conduit facilities necessitated by a Wisconsin Department of Transportation paving project per the Memorandum of Understanding (MOU). (City Share Non-Assessable Paving Fund -- $65,000). These funds are to be transferred to the construction account (ST320052512) (1060-05-77).

The total cost for adjustments to City facilities including this request: $86,900.

The current estimated cost of the total project including ...

Click here for full text