powered help
header-left header-center header-right
File #: 070081    Version:
Type: Resolution Status: Passed
File created: 4/17/2007 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 5/8/2007
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $423,000 for a total estimated cost of these projects being $4,603,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter.pdf
Number
070081
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $423,000 for a total estimated cost of these projects being $4,603,000.
Analysis
This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed. After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable. A resolution will be submitted after the Public Hearing authorizing construction. The City cost for engineering these projects is estimated to be $423,000 with total cost estimated to be $4,603,000.
Body
Resolved, By the Common Council of the City of Milwaukee that it is necessary and in the public interest to do the following described improvements according to city specifications:

3rd Aldermanic District

N. Bartlett Ave. - E. Lafayette Pl. to E. North Ave. (SM495070044): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $20,000) The total estimated cost of this project including this request is $309,000. This project is anticipated to be completed during the 2008 construction season.

N. Bartlett Ave. - E. Thomas Ave. to 167’ +/- north of E. Thomas Ave. (SM495070047): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $11,000) The total estimated cost of this project including this request is $97,000. This project is anticipated to be completed during the 2008 construction season.

N. Cambridge Ave. - E. North Ave. to E. Boylston St. (SM495070050): Relaying and lining combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $13,000) The total estimated cost of this project including this request is $150,000. This project is anticipated to be completed dur...