File #: 061548    Version: 0
Type: Resolution Status: Passed
File created: 3/22/2007 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 4/17/2007
Effective date:    
Title: Resolution directing the City Comptroller to transfer funds and create the appropriate accounts for preliminary engineering for various connecting highway projects with Federal and State Aid with a total estimated cost of $4,158,000, of which the City’s share is $1,039,500 and the grantor’s share is $3,118,500.
Sponsors: THE CHAIR
Indexes: BRIDGES, STATE GRANTS, STREET IMPROVEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Fiscal Note.pdf, 2. Infrastructure Services Division Cover Letter.pdf, 3. Comptroller's Certification.PDF

Number

061548

Version

ORIGINAL

Reference

Sponsor

THE CHAIR

Title

Resolution directing the City Comptroller to transfer funds and create the appropriate accounts for preliminary engineering for various connecting highway projects with Federal and State Aid with a total estimated cost of $4,158,000, of which the City’s share is $1,039,500 and the grantor’s share is $3,118,500.

Analysis

This resolution directs the City Comptroller to transfer funds and set up appropriate accounts for preliminary engineering for the three (3) connecting highway projects and one (1) bridge project (listed below) with Federal/State Aid.  These projects are approved and included in the WISDOT’S current State Trunk Highway program for improvement.  The City is responsible for 25% of the preliminary engineering costs on these projects in accordance with WISDOT policy.  City costs for the construction of these projects will be dependent upon parking allowed.  The estimated total cost of these projects is $29,848,000, of which the City’s share is $2,633,500 and the grantor’s share is $27,214,500.  The total estimated preliminary engineering cost of these projects is $4,158,000, of which the City’s share is $1,039,500 and grantor’s share is $3,118,500.

Body

Whereas, The Common Council of the City of Milwaukee adopted resolution file numbers 041289 and 051477 authorizing the Commissioner of Public Works to execute project agreements with the Wisconsin Department of Transportation (WISDOT) for the programming and construction or rehabilitation of the following connecting highways and bridge projects with Federal and/or State Aid:

 

Aldermanic District                                          Project Location

2, 5, 10                                                               West Capitol Drive (STH 190)

                                                                                         West City Limits to North 60th Street

 

5                                                                                         West Capitol Drive (STH 190)

                                                                                         Bridge over Menomonee River

 

13                                                                                    South Howell Avenue (STH 38)

                                                                                         East Grange Avenue to East Layton Avenue

 

13, 14                                                                                         South Howell Avenue (STH 38)

                                                                                         East Layton Avenue to East Howard Avenue

 

; and

 

Whereas, The improvements scheduled for these connecting highways and bridge are included on the current WISDOT State Trunk Highway Program; and

 

Whereas, South Howell Avenue (STH 38), East Grange Avenue to East Layton Avenue is programmed for construction in 2010; and

 

Whereas, South Howell (STH 38), East Layton Avenue to East Howard Avenue is programmed for construction in 2011; and

 

Whereas, West Capitol Drive (STH 190) and West Capitol Drive Bridge (STH 190) are programmed for construction in 2012; and

 

Whereas, It is the intent to initiate preliminary engineering at this time for these connecting highways and bridge project; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the City Comptroller is hereby authorized to create within the Capital Improvement Fund, Grant and Aid Projects, the necessary Project/Grant Chartfield Values for preliminary engineering for the projects (Expenditures) and transfer to any of these accounts the amount required under the grant agreement and City Accounting Policy but not to exceed a 10 percent increase of the total amounts reserved for the grantor’s share and local share or $5,000, whichever is greater, as follows:

 

Infrastructure Services Division

State I.D. 2060-10-00

South Howell Avenue (STH 38)

East Grange Avenue to East Layton Avenue

 

City Share Non-Assessable Paving

ST320070000

Fund 0333

$180,000

 

Grantor Reimbursable Cash Paving

SP032070100

Fund 0306

$450,000

 

Grantor Non-Reimbursable Paving

SP032070100

Fund 0306

$90,000

 

Construction is scheduled for 2010.

 

Previously authorized for preliminary engineering: -0-

Current estimated cost of total project including this resolution: $4,960,000

Original estimated cost of the total project (Resolution 051477): $4,960,000

 

I.D. 2025-16-00

West Capitol Drive

Bridge over Menomonee River

 

City Share Non-Assessable Paving

ST320070000

Fund 0333

$21,375

 

City Share Non-Assessable Structure

BR300070000

Fund 0303

$64,125

 

Grantor Reimbursable Cash Paving

SP032070100

Fund 0306

$53,438

 

Grantor Reimbursable Cash Structure

SP032070100

Fund 0306

$160,312

 

Grantor Non-Reimbursable Paving

SP032070100

Fund 0306

$10,687

 

Grantor Non-Reimbursable Structure

SP032070100

Fund 0306

$32,063

 

Construction is scheduled for 2012.

 

Previously authorized for preliminary engineering: -0-

Currently estimated cost of total project including this resolution: $2,402,000

Original estimated cost of the total project (Resolution #051477): $2,402,000

 

State I.D. 2060-11-00

South Howell Avenue (STH 38)

East Layton Avenue to East Howard Avenue

 

City Share Non-Assessable Paving

ST320070000

Fund 0333

$54,000

 

Grantor Reimbursable Cash Paving

SP032070100

Fund 0306

$135,000

 

Grantor Non-Reimbursable Paving

SP032070100

Fund 0306

$27,000

 

Construction is scheduled for 2011.

 

Previously authorized for preliminary engineering: -0-

Current estimated cost of total project including this resolution: $3,421,000

Original estimated cost of the total project (Resolution #051477): $3,421,000

 

State I.D. 2025-11-00

West Capitol Drive (STH 190)

West City Limits to North 60th Street

City Non-Assessable Paving

ST32007000

Fund 0333

$720,000

 

Grantor Reimbursable Cash Paving

SP032070100

Fund 0306

$1,800,000

 

Grantor Non-Reimbursable Paving

SP032070100

Fund 0306

$360,000

 

Construction is scheduled for 2012.

 

Previously authorized for preliminary engineering: -0-

Current estimated cost of total project including this resolution: $19,065,000

Original estimated cost of the total project (Resolution #041289): $19,065,000

 

Summary of projects in this resolution:

 

City Non-Assessable Paving ST32007000 Fund 0333 $975,375

City Non-Assessable Structure BR300070000 Fund 0303 $64,125

Grantor Reimbursable Cash Paving SP032070100 Fund 0306 $2,438,438

Grantor Non-Reimbursable Paving SP032070100 Fund 0306 $487,687

Grantor Reimbursable Cash Structure SP032070100 Fund 0306 $160,312

Grantor Non-Reimbursable Structure SP032070100 Fund 0306 $32,063

 

Resolution total: $4,158,000

 

; and, be it

 

Further Resolved, That copies of the State and Federal Aid Agreements are attached to Common Council Resolution File Number 061549, and are incorporated in this resolution by reference as though set forth in full.

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

LCG:amh

March 12, 2007

Reso Cnectg Highwy & Brdgs LCG 030907.rtf