powered help
header-left header-center header-right
File #: 131376    Version:
Type: Resolution Status: Passed
File created: 1/22/2014 In control: COMMON COUNCIL
On agenda: Final action: 2/11/2014
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,104,000 for a total estimated cost of these projects being $2,053,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Hearing Notice List
Number
131376
Version
Substitute 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,104,000 for a total estimated cost of these projects being $2,053,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $1,104,000 with the total cost estimated to be $2,053,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:
 
1st Aldermanic District
 
N. 23rd St. - 310 feet m/l south of W. Hope Ave. to W. Hope Ave. (SM495140005):  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $71,000.  This project is anticipated to be completed during the 2014 construction season.
 
3rd Aldermanic District
 
N. Farwell Av. - E. Brady St. to E. Royall Pl. (SM495120310):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $70,000, Additional Funds).  The total estimated cost for this project including the requested amount is $176,000.  This project is anticipated to be completed during the 2014 construction season.
 
6th Aldermanic District
 
E. Clarke St. - N. Hubbard St. to N. Richards St. (SM495140006):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $83,000.  This project is anticipated to be completed during the 2014 construction season.
 
W. Wright St. - N. Palmer Ave. to N. Buffum St. (SM495140007):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $188,000.  This project is anticipated to be completed during the 2014 construction season.
 
10th Aldermanic District
 
W. Moltke Ave. - W. Appleton Ave. to N. 68th St. (SM495140003):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $314,000.  This project is anticipated to be completed during the 2014 construction season.
 
N. 64th St. - 160 feet south of W. Moltke Ave. to W. Moltke Ave. (SM495140002):  Relaying sanitary sewer and storm repair.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $38,000.  This project is anticipated to be completed during the 2014 construction season.
 
12th Aldermanic District
 
W. Oregon St. - S. 6th St. to 50 feet m/l west of S. 6th St. (SM495140004):  Combined relocation.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $63,000.  This project is anticipated to be completed during the 2014 construction season.
 
City Wide
 
2014 Indirect Account (SM495140001):  (Nonassessable Sewer Maintenance Relay Fund -- $800,000).  The total estimated cost for this project is $800,000.  This project is anticipated to be completed during the 2014 construction season.
 
Various Aldermanic Districts
 
Water Alterations - Developer Funded (WT430140300):  Alterations.  (Nonassessable Water Fund Budget Line 5010 -- $25,000; Nonassessable Water Fund Budget Line 5010 -- $25,000).  The total estimated cost for this project is $50,000.  This project is anticipated to be completed during the 2014 construction season.
 
Alterations by Milwaukee Water Works Distribution (WT410140730):  Alterations.  (Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project including the requested amount is $50,000.  This project is anticipated to be completed during the 2014 construction season.
 
Water Main Alterations by Private Contractor (WT410140750):  Water main alteration.  (Nonassessable Water Fund Budget Line 5010 -- $7,000; Nonassessable Water Fund Budget Line 6410 -- $8,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2014 construction season.
 
Water Main Alterations by Private Contractor prior to paving (WT410140770):  Water main alteration.  (Nonassessable Water Fund Budget Line 5010 -- $4,000; Nonassessable Water Fund Budget Line 6410 -- $5,000).  The total estimated cost for this project including the requested amount is $50,000.  This project is anticipated to be completed during the 2014 construction season.
 
Post Guarantee Inspections (WT440140850):  Inspection.  (Nonassessable Water Fund Budget Line 5010 -- $5,000).  The total estimated cost for this project is $5,000.  This project is anticipated to be completed during the 2014 construction season.
 
Water Main Material Inspection (WT410140880):  Inspection.  (Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project is $15,000.  This project is anticipated to be completed during the 2014 construction season.
 
Various Suburbs
 
Review of Consultant Prepared Suburban Construction Plans (WT440140800):  Plan review.  (Nonassessable Water Fund Budget Line 5010 -- $30,000; Nonassessable Water Fund Budget Line 6410 -- $20,000).  The total estimated cost for this project is $50,000.  This project is anticipated to be completed during the 2014 construction season.
 
;and, be it
 
Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it
 
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
 
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
 
Requestor
Infrastructure Services Division
Drafter
MLD:dr
Npr 7
01/24/2014