File #: 060572    Version:
Type: Resolution Status: Passed
File created: 9/6/2006 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 9/26/2006
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,828,000 for a total estimated cost of these projects being $1,946,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. DPW-Infrastructure Services Division Cover Letter.pdf, 2. Sub. 1 Fiscal note, 3. Sub. 2 Fiscal note
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
10/5/20062 MAYOR SIGNED   Action details Meeting details Not available
9/26/20062 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
9/13/20062 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
9/13/20061 PUBLIC WORKS COMMITTEE AMENDED

Minutes note: Ald. Bauman moved to amend by deleting the following: 4th and 15th Aldermanic Districts N. 20th St. - W. Cherry St. to W. Walnut St. (WT410061129) File Number 051222: Relay water main. (Nonassessable Water Fund -- $245,000). File Number 051222 authorized $15,000. The total estimated cost for this project including the requested amount is $260,000. This project is anticipated to be completed during the 2007 construction season. 11th Aldermanic District S. 31st St. - W. Drury Ln. to W. Paine St. (WT410061031) File Number 041695: Relay water main. (Nonassessable Water Fund -- $55,000). File Number 041695 authorized $10,000. The total estimated cost for this project including the requested amount is $65,000. This project is anticipated to be completed during the 2007 construction season. S. 37th St. - W. Ohio Ave. to W. Morgan Ave. (SM495060038) File Number 060243: Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $213,000) File Number 060243 authorized $10,000. The total estimated cost for this project including the requested amount is $223,000. This project is anticipated to be completed during the late 2006 construction season. S. 40th St. - W. Euclid Ave. to 200 feet m/l south of W. Euclid Ave. (WT410061015) File Number 041695: Relay water main. (Nonassessable Water Fund -- $50,000). File Number 041695 authorized $10,000. The total estimated cost for this project including the requested amount is $60,000. This project is anticipated to be completed during the 2007 construction season.
Pass5:0 Action details Meeting details Not available
9/13/20062 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass5:0 Action details Meeting details Not available
9/8/20061 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
9/8/20060 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
9/6/20060 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
060572
Version
SUBSTITUTE 2
Reference
050136
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,828,000 for a total estimated cost of these projects being $1,946,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $1,828,000. The total estimated cost of these projects is $1,946,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

3rd Aldermanic District

E. Ivanhoe Pl. - N. Summit Ave. to N. Lake Dr. (SM495050028) File Number 050136: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $69,000) File Number 050136 authorized $10,000. The total estimated cost for this project including the requested amount is $79,000. This project is anticipated to be completed during the 2006/2007 construction season.

N. Summit Ave. - E. Kenilworth Pl. to E. North Ave. (SM495060017) File Number 051658: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $224,000) File Number 051658 authorized $12,000. The total estimated cost for this project including the requested amount is $236,000. This project is anticipated to be completed during the 2006/2007 construction season.

E. Wyoming Pl. - N. Summit Ave. to N. Lake Dr. (SM495060019) File Number 051658: Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $34,000) File Number 051658 authorized $4,000. The total estimated cost for this...