powered help
header-left header-center header-right
File #: 060370    Version:
Type: Resolution Status: Passed
File created: 7/12/2006 In control: PUBLIC WORKS COMMITTEE
On agenda: 7/19/2006 Final action: 7/31/2006
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $80,000 for a total estimated cost of these projects being $215,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter.pdf, 2. Fiscal Note
Number
060370
Version
SUBSTITUTE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $80,000 for a total estimated cost of these projects being $215,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $80,000 with the total cost estimated to be $215,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

3rd Aldermanic District

Cherry Street Bascule Bridge (BR100060104): Bridge repairs and repairs to the northwest retaining wall. (City Share Non-assessable Structure Fund -- $50,000). The total estimated cost for this project including the requested amount is $50,000. This project is anticipated to be completed during the 2006/2007 construction season.

4th Aldermanic District

W. McKinley Bl. - N. 27th St. to N. 35th St. (ST211060181): Install traffic calming speed humps. The total estimated cost for this project is $15,000. This project is anticipated to be completed during the 2006 construction season.

12th Aldermanic District

W. Scott St. - S. 4th St. to S. 6th St. (WT410061064): Installing butterfly valve. (Nonassessable Water Fund -- $15,000). The total estimated cost for this project including the requested amount is $40,000. This project is anticipated to be completed during the spring of 2007 construction season.

15th Aldermanic District

N. 24th St. - W. North Ave. to W. Medford Ave. (WT410061063): Relaying water main. (Nonassessable Water Fund -- $15,00...