Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $113,000 for a total estimated cost of these projects being $2,089,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $113,000 with the total cost estimated to be $2,089,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:
3rd Aldermanic District
N. Summit Ave. - E. Kenwood Blvd. to E. Hartford Ave. (SM495060040): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000). The total estimated cost for this project including the requested amount is $250,000. This project is anticipated to be completed during the 2007 construction season.
7th and 15th Aldermanic Districts
W. Locust St. - N. 29th St. to the Soo Line Railroad Right of Way (SM495060042): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $5,000). The total estimated cost for this project including the requested amount is $142,000. This project is anticipated to be completed during the 2007 construction season.
8th Aldermanic District
S. 23rd St. - W. Scott St. to W. Greenfield Ave. (SM495060045): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $9,000). The total estimated cost for this project including the requested amount is $118,000. This project is anticipated to be completed during the 2007 construction season.
10th Aldermanic District
W. McKinley Ave. - N. 55th St. to 150 feet m/l west of N. 55th St. (SM495060046): Relaying sanitary and storm sewers. (Nonassessable Sewer Maintenance Relay Fund -- $7,000). The total estimated cost for this project including the requested amount is $71,000. This project is anticipated to be completed during the 2007 construction season.
N. 55th St. - 235 feet m/l south of W. McKinley Ave. to W. McKinley Ave. (SM495060037): Relaying sanitary and storm sewers. (Nonassessable Sewer Maintenance Relay Fund -- $10,000). The total estimated cost for this project including the requested amount is $98,000. This project is anticipated to be completed during the 2007 construction season.
11th Aldermanic District
S. 37th St. - W. Ohio Ave. to W. Morgan Ave. (SM495060038): Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $10,000). The total estimated cost for this project including the requested amount is $96,000. This project is anticipated to be completed during the 2006/2007 construction season.
12th Aldermanic District
S. 8th St. - W. Lincoln Ave. to W. Arthur Ave. (SM495060041): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost for this project including the requested amount is $204,000. This project is anticipated to be completed during the 2007 construction season.
14th Aldermanic District
S. Clement Ave. - E. Holt Ave. to E. Warnimont Ave. (SM495060029): Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $5,000). The total estimated cost for this project including the requested amount is $484,000. This project is anticipated to be completed during the 2006/2007 construction season.
S. Logan Ave. - E. Dakota St. to E. Idaho St. (SM495060043): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $5,000). The total estimated cost for this project including the requested amount is $75,000. This project is anticipated to be completed during the 2007 construction season.
E. Nock St. - 150 feet m/l east of S. Shore Dr. to S. Shore Dr. (SM495060036): Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $5,000). The total estimated cost for this project including the requested amount is $20,000. This project is anticipated to be completed during the 2006 construction season.
15th Aldermanic District
W. Center St. - N. 9th St. to N. 13th St. (SM495060039): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $20,000). The total estimated cost for this project including the requested amount is $366,000. This project is anticipated to be completed during the 2007 construction season.
N. 32nd St. - W. Meinecke Ave. to W. Wright St. (SM495060044): Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost for this project including the requested amount is $165,000. This project is anticipated to be completed during the 2007 construction season.
; and, be it
Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.