powered help
header-left header-center header-right
File #: 051539    Version:
Type: Resolution Status: Passed
File created: 3/23/2006 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 4/11/2006
Effective date:    
Title: Substitute resolution determining it necessary to make various assessable public improvements at various locations. The City cost for engineering this project is estimated to be $15,000.
Sponsors: THE CHAIR
Indexes: SEWER IMPROVEMENTS, SEWERS, WATER MAINS
Attachments: 1. Infr. Serv. Div. Cover Letter.pdf, 2. Fiscal Note.pdf, 3. Sub Fiscal Note

 

Number

051539

Version

SUBSTITUTE 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various assessable public improvements at various locations. The City cost for engineering this project is estimated to be $15,000.

Analysis

This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed.  After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable.  A resolution will be submitted after the Public Hearing authorizing construction.  The City cost for engineering this project is estimated to be $15,000 with a total cost to be $210,000.  Construction of this project is anticipated to be in the spring of 2007.

Body

Resolved, By the Common Council of the City of Milwaukee that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.60 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:

 

5th Aldermanic District

 

W. Appleton Ave. - 1750 feet m/l southeast of N. 124th St. to 1010 feet m/l southeast of N. 124th St. (WT410061132):  Water main extension. (Nonassessable Water Fund -- $15,000).  The City cost of this project including the requested amount is estimated to be $210,000.  Construction of this project is anticipated to be in the spring of 2007.

 

; and, be it

 

Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it

 

Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

mld:lk

apr9

03/29/06