File #: 040149    Version: 0
Type: Resolution Status: Passed
File created: 5/25/2004 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 6/15/2004
Effective date:    
Title: Resolution authorizing the Commissioner of Public Works to execute an agreement with the Wisconsin Department of Transportation for the funding of the installation of interim street lighting, installation of permanent lighting improvements, and the removal of the interim lighting in the area bounded by West Wisconsin Avenue, West Walnut Street, North 7th Street and North 13th Street and adjoining streets in conjunction with Marquette Interchange reconstruction. (Infrastructure Services Division)
Sponsors: THE CHAIR
Indexes: AGREEMENTS, STREET LIGHTING, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Fiscal Note.pdf, 2. Infr. Serv. Div. Cover Letter.pdf, 3. Contract.PDF, 4. Cost Estimate.PDF, 5. Fiscal Analysis.pdf
Number
040149
Version
ORIGINAL
Reference

Sponsor
THE CHAIR
Title
Resolution authorizing the Commissioner of Public Works to execute an agreement with the Wisconsin Department of Transportation for the funding of the installation of interim street lighting, installation of permanent lighting improvements, and the removal of the interim lighting in the area bounded by West Wisconsin Avenue, West Walnut Street, North 7th Street and North 13th Street and adjoining streets in conjunction with Marquette Interchange reconstruction. (Infrastructure Services Division)
Analysis
This resolution authorizes the Commissioner of Public Works to install interim street lighting facilities, to install permanent street lighting facilities and remove interim street lighting facilities in the area bounded by West Wisconsin Avenue, West Walnut Street, North 7th Street and North 12th Street and adjoining streets in conjunction with the next stage of reconstruction of the Marquette Interchange known as the North Contract. Funding for the construction of the street lighting improvements is to be provided by the Wisconsin Department of Transportation under the Federally funded State Highway Improvement Program as part of the interchange project.
Body
Whereas, The Wisconsin Department of Transportation is reconstructing the Marquette interchange of IH 94, USH 41, IH43, and IH 794 under the State Highway Improvement Program; and

Whereas, The Interchange reconstruction project provides cost participation for street lighting improvements; and

Whereas, The total estimated cost of street lighting improvements included as part of this project is; $742,381.58; and

Whereas, A maximum of ten percent of the participating project cost, or $74,238.16, is non-reimbursable and is included in the Division's 2004 Capital Purpose Account, Project/Grant Number ST240040000; and

Whereas, A minimum of ninety percent of the participating project cost, or $668,143.42, is rei...