File #: 130952    Version:
Type: Resolution Status: Passed
File created: 11/5/2013 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 11/26/2013
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $2,520,700 for a total estimated cost of $5,928,405.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. Transmittal Letter, 2. Actions on Official Notice Number 41, 3. Official Notice Number 41, 4. Hearing Notice List, 5. Capitol Grant Reso. Cert. No. 130952.PDF, 6. Notice Published on 12-16-13
Number
130952
Version
SUBSTITUTE 1
Reference
111697
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $2,520,700 for a total estimated cost of $5,928,405.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $2,520,700. The total estimated cost of these projects is $5,928,405.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

1st Aldermanic District

W. Hampton Ave. - N. Green Bay Ave. to N. Teutonia Ave. (ST320100801) (2545-03-01) File Number 111697 and 100021: Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, tree removals where necessary, sodding (6-foot width of tree border area), and grading.

Grantor Non-Reimbursable Paving Fund -- $2,048,306
Grantor Reimbursable Paving Fund -- $282,042
City Share Non-assessable Paving Fund -- $680,100
City Share Assessable Paving Fund -- $21,000

These funds are to be transferred to the construction account (ST3201008xx)
(2545-03-71).

Previously authorized for project construction: $0.00

Current estimated cost of total project including this resolution: $3,936,405

Original estimated cost of the project: $3,842,935

This project is anticipated to be completed during the 2014 construction season.