File #: 130921    Version: 0
Type: Resolution Status: Passed
File created: 11/5/2013 In control: COMMON COUNCIL
On agenda: Final action: 11/26/2013
Effective date:    
Title: Resolution relative to the cost participation and installation of traffic signal improvements under four Congestion Mitigation Air Quality projects in various Aldermanic Districts at a total estimated cost of $246,723.54, with an estimated grantor share of $197,378.83, and an estimated City share of $49,344.71.
Sponsors: THE CHAIR
Indexes: GRANTS, TRAFFIC CONTROL SIGNALS
Attachments: 1. Agreement for Construction - Capitol and Fond du Lac, 2. Project Unit Cost Analysis - Capitol and Fond du Lac, 3. Agreement for Construction - 34 Intersections, 4. Project Unit Cost Analysis - 34 Intersections, 5. Agreement for Construction - 25 Intersections, 6. Project Unit Cost Analysis - 25 Intersections, 7. Agreement for Construction - 10 Intersections, 8. Project Unit Cost Analysis - 10 Intersections, 9. Comptrollers Certificate, 10. Signed Agreement, 11. Second Signed Agreement, 12. Hearing Notice List
Number
130921
Version
ORIGINAL
Reference

Sponsor
THE CHAIR
Title
Resolution relative to the cost participation and installation of traffic signal improvements under four Congestion Mitigation Air Quality projects in various Aldermanic Districts at a total estimated cost of $246,723.54, with an estimated grantor share of $197,378.83, and an estimated City share of $49,344.71.
Analysis
This resolution authorizes the Commissioner of Public Works and Comptroller to execute four Local Force Account agreements with the Wisconsin Department of Transportation for the installation of traffic signal improvements using City forces at various intersections citywide under four Congestion Mitigation Air Quality projects in various Aldermanic Districts at a total estimated cost of $246,723.54, with an estimated grantor share of $197,378.83, and an estimated City share of $49,344.71. This resolution also authorizes the Comptroller to establish and transfer funds to the appropriate accounts for the project. The total cost of all four projects is $1,033,620, with a grantor share of $826,896, and a City share of $206,724.
Body
Whereas, Four Project Agreements for the installation of traffic signal improvements under the 2013 Congestion Mitigation Air Quality program were approved by the Common Council under File Number 110136; and

Whereas, The projects include the installation of signal improvements including pedestrian and vehicle detection or optimized traffic signal timings at various intersections Citywide; and

Whereas, The Congestion Mitigation Air Quality program is intended to reduce traffic congestion and vehicle emissions; and

Whereas, The total estimated cost of the four projects is $228,766.95 for traffic control signal improvements; and

Whereas, $49,344.71 is not reimbursable and is included in the Division's 2013 Capital Purpose Project Grant Number ST320130000; and

Whereas, $197,378.83 is reimbursable from the Wisconsin Department of Transportat...