powered help
header-left header-center header-right
File #: 990528    Version:
Type: Resolution Status: Passed
File created: 7/13/1999 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 7/29/1999
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
Sponsors: THE CHAIR
Indexes: ALLEY IMPROVEMENTS, PUBLIC IMPROVEMENTS, SIDEWALKS, SPECIAL ASSESSMENTS
NUMB:
990528
VERS:
SUBSTITUTE 1
REF:
981611
XXBY:
THE CHAIR
TITL:
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
ANLS:
-Analysis-
 
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.
BODY:
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
 
3rd Aldermanic District
 
Alley between N. Downer Ave., E. Newberry Blvd., E. Park Pl., and N. Stowell Ave. (East-West Leg) ST21200145 (880-0855-4) File Number 981611: Concrete alley pavement reconstruction, replace some abutting sidewalk and driveway approaches where needed, and grading. (Nonassessable Alley Paving Fund -- $21,710; Assessable Alley Paving Fund -- $5,390)
 
15th Aldermanic District
 
Alley between W. Carmen Ave., W. Thurston Ave., N. 96th St., and N. 97th St. ST21200117 (888-0720-8) File Number 960973: Concrete alley pavement reconstruction, replace some abutting sidewalk and driveway approaches, storm water drainage facilities where needed, and grading. (Nonassessable Alley Paving Fund -- $61,370; Assessable Alley Paving Fund -- $33,565)
 
; and
 
Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and
 
Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it
 
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works' Report, as amended at said Public Hearing, is approved and the properties therein identified are benefitted; and, be it
 
Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.60 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
 
Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
 
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it
 
Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it
 
Further Resolved, That projects Alley between W. Downer Ave. (880-0855-4) and Alley between W. Carmen Ave. (888-0720-8) will be billed after January 1, 2001, but not before 12 months after the project contract has been completed.
 
 
DFTR:
INFRASTRUCTURE SERVICES DIVISION
CAW:lmh
07-21-99
AFR15.1