File #: 981266    Version: 0
Type: Resolution Status: Passed
File created: 12/18/1998 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 1/19/1999
Effective date:    
Title: Resolution determining it necessary to make various assessable public improvements at various locations. (Infrastructure Services Division)
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SIDEWALKS, STREET IMPROVEMENTS

NUMB:

981266

VERS:

ORIGINAL

XXBY:

THE CHAIR

TITL:

Resolution determining it necessary to make various assessable public improvements at various locations. (Infrastructure Services Division)

ANLS:

-Analysis-

 

This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed. After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable. A resolution will be submitted after the Public Hearing authorizing construction.

BODY:

Resolved, By the Common Council of the City of Milwaukee that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.60 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:

 

3rd Aldermanic District

 

E. North Ave. - N. Prospect Ave. to the Milwaukee River (842-0077-4): SPECIAL TREATMENT: Paving the roadway with concrete. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work.

 

7th Aldermanic District

 

N. 44th St. - W. Clarke St. to W. Center St. (Widening on E/S) (879-0896-7): Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work.

 

9th Aldermanic District

 

N. Range Line Rd./N. 27th St. - W. Good Hope Rd. to N. Green Bay Ave. (892-0169-6): Paving the roadway with concrete. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work.

 

13th Aldermanic District

 

E. Armour Ave. (S/S) - S. Austin St. to point East of S. Howell Ave. (839-0897-7): Laying concrete sidewalk. Doing all the necessary grading pertaining to said work.

 

;and, be it

 

Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it

 

Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works.

DFTR: